Proposed · Documented · Location approximate
Not suspended. Crusoe withdrew, and Google resubmitted a smaller site plan, which the county said in July 2026 it would process administratively. Google announced the project Nov. 5, 2026. Reports in September 2026 said the campus had not broken ground and site development could begin by year's end, though a June report said site clearing had begun earlier in 2026. The adjacent gas plant is under construction, per the county.
Google, as Jupiter Star Holdings, LLC. Related Digital is lead developer, reports say. Tallgrass Energy builds the adjacent gas plant. Crusoe, the original applicant, withdrew
Switchgrass Industrial Park, Section 5, T12N, R66W, west of US 85, about 1 mile south of Terry Ranch Road and about 8 miles south of Cheyenne, Laramie County, Wyoming. The point is the central coordinate in the January 2026 Project Jade site plan, rounded. That plan predates Google's revision.
No document read gives the Google campus's own capacity. Google's announcement doesn't state one.
Black Hills' SEC filing says the project is expected to be served by a total resource mix of 2.7 GW, including reserve margins, with service starting in late 2027 and reaching peak load in 2030. That is supply, not use.
Crusoe's earlier plan was reported as 1.8 GW, able to grow to 10 GW pending further approvals. Google's plan is smaller, and its capacity hasn't been stated. Some reports still apply 2.7 GW to the data center itself.
Sources describe grid use differently. Google told residents the data centers would be kept off the local Cheyenne grid, Oil City News reports. Black Hills' SEC filing describes up to 590 MW of "grid-connected" service.
Backup: diesel generators would need a Wyoming DEQ air permit, Wyoming Public Media reports. No permit was found.
It isn't confirmed whether AEP's 702 MW is part of the 2.1 GW of third-party resources Black Hills will manage, Data Center Frontier reports.
Black Hills: contracts effective Sept. 30, 2026, through 2048. Up to 590 MW of grid-connected service, including 564 MW nameplate of new gas generation at Cheyenne Prairie Generating Station. Black Hills will also manage about 2.1 GW of third-party resources through a private microgrid.
Cheyenne Prairie expansion: state notice shows growth from 140 MW to 692 MW, with a contested siting hearing set for Nov. 9, 2026. The notice names neither Google nor a data center; Black Hills' SEC filing makes the link. Black Hills says the air permit was approved in August 2026.
Tallgrass: BFC Power and Cheyenne Power Hub, two power generation facilities on the adjacent 659-acre Section 7. County site plan approved Jan. 6, 2026; the county says construction phases are well underway. POWER reports 2.7 GW of gas generation. Google says it is sourcing power from Tallgrass and Black Hills gas generators.
AEP: a 702 MW Bloom fuel cell project near Cheyenne under a 20-year agreement with Google, about $4 billion, fully running by end of 2028 per AEP. Google says carbon capture is part of the plan, with storage at Tallgrass's Eastern Wyoming Sequestration Hub. AEP's release doesn't name the campus; Google's announcement ties it to the Wyoming project.
Air-cooled, per Google's Nov. 5, 2026 announcement. Google described air-cooled, closed-loop cooling at its September open house. Crusoe's earlier plan also called for closed-loop cooling.
Deep wells in the Lance Formation aquifer, about 1,500 feet down, not city water. Google projected 20-30 million gallons a year in September 2026, with wastewater treated on site and sent to lined evaporation ponds. These are company figures, as reported.
At the Jan. 6, 2026 hearing, residents raised groundwater contamination and use, traffic, lighting and views. The Hyndman Heights HOA's Randy Fox questioned whether the Lance Formation had been surveyed enough. Chamber, union, governor's office and petroleum group speakers supported it. The board voted 5-0.
The Hyndman Homesites HOA also wrote about deep wells, noise, light, turbine emissions, odors and wastewater ponds, WyoFile reports.
The nearest home is 0.1 mile east, per Google's filing as reported. A neighbor at Google's open house asked about a planned road near his property and whether a nearby house, where he said relatives once lived, would be torn down. Google answered yes to both, Wyoming Public Media reports.
At the September 2026 meetings, people raised stormwater, lighting, diesel generator pollution and noise, and said the South Side is already strained by data center growth.
Google says it did not pursue a local incentive, will replenish 120% of the water it consumes through watershed projects, and expects hundreds of millions in property taxes. These are company claims.
Name: "Project Braid" is not this site's name. Bloomberg says it is the internal name for Crux AI, the $5 billion Google and Blackstone venture to rent out Google AI chips. Bloomberg calls Google's scrapping of Crusoe's Cheyenne plan an early snag for that venture. Footprint has not confirmed this campus will serve it.
One outlet reported the "outright scrapping" of a Cheyenne project. County records and later filings show Crusoe's role ended, not the project. Crusoe told Bloomberg it paused at its customer's request; Black Hills said the project had not been paused.
Scale change, per the county: from five buildings and 4,025,500 sq ft to four buildings and 3,080,000 sq ft, with peak construction workforce down from 5,000 to 2,500.
Google's plan adds a two-story office building on 32.83 acres. The Planning Commission approved its permit on Sept. 10, 2026, according to Cap City News.
The 1,375-acre park was zoned on Oct. 7, 2025, on Tallgrass's application. Google's investment is $17 billion by its own figure; a 2026 trade report put Crusoe's plan above $50 billion.
Last checked 2026-11-05.