Under construction · Documented · Location approximate
Related Digital said in April 2026 that construction on the first buildings was underway and on schedule for delivery to Oracle. A ceremonial groundbreaking with OpenAI's Sam Altman and Gov. Gretchen Whitmer was held June 1, 2026, WXYZ reports. Epoch AI's satellite timeline shows groundwork for Building 1 by March 2026 and projects Buildings 1 to 3 running by the end of 2028.
Related Digital, developer, with equity from Blackstone-affiliated funds. Built for Oracle, as part of Oracle's work with OpenAI. DTE's contract customer is Green Chile Ventures LLC, an Oracle subsidiary
North of Michigan Avenue (US-12), Saline Township, Washtenaw County, Michigan. Related Digital says the main entrance is on Michigan Avenue, by a historic red barn. No source read gives a street address. The point is FracTracker's location for this listing, rounded.
Michigan's Public Service Commission describes "the 1,383-megawatt (MW) data center" in its Dec. 18, 2025 approval of two DTE Electric contracts with Green Chile Ventures (Case No. U-21990). The order requires a 19-year minimum term and minimum billing of 80% of contracted use. The Attorney General calls it a 1.4 gigawatt data center. These are the size of the planned supply contracts, not measured use.
Related Digital describes three single-story data center buildings "with more than a gigawatt of capacity". It says DTE will supply 100% of the power from existing resources plus new battery storage paid for entirely by Oracle.
Backup: Michigan's environment agency (EGLE) issued an air permit on Jan. 13, 2026 for 14 diesel backup generators and a diesel fire pump, Planet Detroit reports, with expected nitrogen oxides of 34.86 tons a year. It says backup covers about 1% of the power load.
Grid, approved with conditions: the Michigan PSC conditionally approved DTE Electric's special contracts to supply the data center on Dec. 18, 2025 (Case No. U-21990). DTE must cover any costs to serve the site it can't recover from Green Chile Ventures, and the data center's load would be cut before other customers' in an emergency. The Attorney General appealed the approval to the Michigan Court of Appeals on April 17, 2026; Footprint found no ruling.
Closed-loop cooling, per Related Digital. Related told Fortune the system won't use evaporative cooling and ongoing water use will be comparable to a standard office building. These are company claims.
The township board voted 4-1 in September 2025 against rezoning 575 acres of farmland. Related Digital and the landowners sued on Sept. 12, alleging exclusionary zoning, and the township settled. The settlement includes about $14 million in community benefits and limits on water use, noise and expansion, according to Fortune.
Residents' concerns include groundwater and runoff, since many rely on private wells. Resident Kathryn Haushalter has fought the project in court, and resident E. Frederick Gall began a recall of three board members, Fortune reported in May 2026. Footprint hasn't found how either ended.
Wetlands: EGLE's Jan. 16, 2026 permit allows a stream disturbance, a culvert and stormwater outfalls to the Saline River and nearby drains. Planet Detroit reports 9.12 acres of wetlands lost, with 13.68 acres of mitigation in the River Raisin watershed.
Politics: both main candidates for governor in 2026 called for a moratorium on new projects while lawmakers write rules, Michigan Public reported in October. Republican John James campaigned at the site and wants data centers on existing industrial land, not farmland.
Cost: Related Digital and Fortune give $16 billion. Planet Detroit's earlier report gave $7 billion. Fortune describes 21 million square feet; Related describes three single-story buildings.
Related Digital says 250 acres are developed, and 750 or more acres will be kept as open space, farmland and wetlands. Planet Detroit adds 475 acres in Bridgewater Township that won't be developed.
Jobs, per Related Digital: 2,500 or more union construction jobs and 450 or more on-site jobs.
OpenAI's Sam Altman referred to "one gigawatt" at the June 2026 groundbreaking, WXYZ reports. The companies also gave $10 million to the Saline Recreation Center.
Last checked 2026-11-11.