Operating · Documented · Location approximate
Only part of the park is running. YTL's page says its first 72 MW data center is operating. Epoch AI's imagery shows Buildings 1 and 2 complete and more under construction as of July 2026.
YTL Power International, through YTL Data Center
Kulai, Johor. YTL gives road directions (Kulai Toll, then about 8 km on Jalan Sawah), not an address. The point marks Jalan Sawah on OpenStreetMap, not the park.
The June 2026 analyst note says YTL is working with TNB to secure an extra 600 MW of supply, and that 298 MW is contracted, about 70% of it handed over to customers.
Grid: YTL's page says the park has access to national grid power. It does not describe the connection.
On-site generation, planned: YTL's 2024 release describes 500 MW of on-site solar to supply the facility. The June 2026 analyst note says a 600 MW solar farm is planned, with 215 MW under development.
Liquid-cooled Nvidia GB200 systems in the first AI facility, per YTL's statement in The Edge. Epoch AI counts 47 evaporative cooling towers on satellite imagery.
Not named. YTL's page says the park has access to water resources.
YTL says its Nvidia-based AI facility was completed in late 2025 and will host government and citizen-facing AI services, which with Epoch AI's listing is which is why it is marked as an AI site.
In August 2026 YTL Power and JLand announced a separate campus of up to 1.3 to 1.5 GW at Sedenak Tech Park West, as reported by w.media. It isn't part of this record.
Last checked 2026-11-04.