On August 6, 2025, Tucson's mayor and council voted that they "will not consider or approve Project Blue as it has been proposed." The city ended talks on annexation and a development agreement. Project Blue's site lies just outside the city, in unincorporated Pima County, and the project kept going.
The site is 290 acres west of Houghton Road, and the developer is Beale Infrastructure. Pima County describes about 10 buildings and up to $3.6 billion.
The original plan relied on reclaimed water. A June 2025 county memo described cooling sustained by 100% reclaimed water. Tucson put build-out demand at about 1,910 acre-feet of reclaimed water a year across two sites.
After the city's vote, Beale described something different: an air-cooled closed-loop system that "will consume no water, potable or otherwise, for industrial cooling." That's a design claim. Nothing has been built that would test it.
In December 2025, county and city leaders said that Amazon was no longer the expected user. Beale said Amazon had shown interest but never signed an agreement. The end user still isn't public.
On December 3, the Arizona Corporation Commission approved a deal between Tucson Electric Power and the project by 4-1. It covers up to 286 MW for the first phase. Beale's letter says service can begin in May 2027 and ramp up over 18 months. KGUN reports that the utility estimates up to 600 MW at full build-out.
Attorney General Kris Mayes appealed the deal in Maricopa County Superior Court. Footprint hasn't found a ruling.
A judge dismissed the No Desert Data Center Coalition's lawsuit over the rezoning in April 2026, and site work had begun by that month.
On April 24, Tucson Water revoked a contractor's construction meter, and the city manager later asked Beale to replace two acre-feet of water used at the site. Beale said the city had issued the permit in the normal course of business.
On May 13, Pima County cited the contractor, Ames Construction, for violating its dust permit. Beale said site work was "temporarily paused while the contractor formalizes a non-potable water source."
The state water agency approved two on-site wells. Together they're capped at 96.5 acre-feet a year, about 31.4 million gallons. Beale's own claim is much lower: 15,000 to 20,000 gallons a day after one fill of the cooling loop. Neither is measured use, because the site isn't running.
Dr. Sharon Megdal of the University of Arizona told KGUN the site will probably use far less than the cap, and called it "an unusual situation."
In August 2026, KJZZ wrote that the project "continues breaking ground." Footprint hasn't found a later construction report. Pima County's 120-day pause on new data centers, from September 2026, exempts Project Blue, according to a local newsletter.
Still open: who the customer is, how the attorney general's appeal ends, and how much water the site will really use. Tucson's vote didn't stop a project outside its limits. Other local fights have ended differently.