Last checked 2026-11-05. Compiled with AI help and checked against the linked documents.
One plan was denied at 2:14 in the morning. One lost 7-0, with city staff recommending denial. One was undone by a defect in a public notice, after being reported as planned to be the world's largest data center complex. These three are from Footprint's records, which are selected sites, not a representative sample, so they don't show how often local fights succeed.
The Highlander proposal was for five buildings on nearly 200 acres between San Marcos and New Braunfels, at about $1.5 billion, according to the Austin Chronicle.
Drought was part of the local debate. The Hays County judge has pushed for a pause on high-water-use projects, and a local river group said "we are out of water," the Chronicle reported.
For the vote, Texas Public Radio reported, hundreds attended and 125 people signed up to speak. The council denied the land use change 5-2 at 2:14 a.m. on February 18, 2026.
The Price Road Innovation Campus would have included a three-story AI data center and five research or office buildings, on a site the city's minutes put at about 40 acres.
The mayor told KJZZ the city got over 250 emails against and 10 in support. Former U.S. Sen. Kyrsten Sinema urged approval at earlier meetings. City staff recommended denial, while the Planning and Zoning Commission voted 5-1 to approve.
The council denied it 7-0 on December 11, 2025. Mayor Kevin Hartke said it "does not align with the city's current general plan."
The Prince William Digital Gateway was to sit along Pageland Lane, next to Manassas National Battlefield Park, with as many as 37 data centers planned. Opponents raised harm to the watershed, wildlife and the park's historic feel. Oak Valley Homeowners Association and the American Battlefield Trust led the challenges.
The court's ruling turned on notice. On March 31, 2026, Virginia's Court of Appeals held the three rezonings void from the start, over defective public notice. Compass and the county withdrew, and in July 2026 QTS withdrew its final appeal, saying it had decided to end the project.
In San Marcos, the developer could have refiled after six months, and part of the site was outside city limits. Footprint hasn't found a refiling. The city banned data centers from its limits by a 4-3 vote in June 2026, and a state senator plans to challenge the ban, The Real Deal reported.
In Chandler, KJZZ said at the time it wasn't clear what the company would do with the property. The city said in 2026 it wants other uses there.
And a local no doesn't always stop a project. Tucson rejected Project Blue, and it moved ahead outside the city. More cases are in the finding on local fights.