Price Road Innovation Campus (rejected)

Cancelled · Documented · Location confirmed

Chandler's council denied the rezoning and development agreement 7-0 on Dec. 11, 2025. KJZZ said at the time it wasn't clear what the company would do with the property; the city said in 2026 it wants other uses there.

Operator

Active Infrastructure, applicant. Development agreement named BA Price Owner LLC. No tenant named

Location

3380 S. Price Road, Chandler, AZ 85248

Southwest corner of Price and Dobson roads, about 40 acres, in Chandler. The point comes from the Census geocoder and marks the address, not the building outline.

Power

Would have needed a contract with Salt River Project for 230-kilovolt lines to the site, with power expected around 2031-2032. The city said the Price Corridor had about 80 MW available, and a user over 10 MW must go through an SRP study. No MW figure for the project itself was found in the minutes.

Cooling

Proposed only, never built. The development agreement would have required mechanical or closed-loop cooling, per the city's economic development director. The site's existing building has evaporative cooling.

Water

City of Chandler water, proposed. The water resources manager told the council the data center would be limited to about 48,000 gallons a day on average (the applicant's figures: 48,631 average, 97,262 peak) and the five other buildings to roughly 30,000. A one-inch meter would physically cap delivery near 50,000 gallons a day. For comparison, she said the vacant site now uses about one million gallons a month for its existing evaporative cooling. These are limits and a city statement, not measurements of a data center.

Community

Residents opposed it. The mayor told KJZZ the city got over 250 emails against and 10 in support. Former U.S. Sen. Kyrsten Sinema urged approval at earlier meetings. Staff recommended denial as inconsistent with city plans, and the Planning and Zoning Commission voted 5-1 to approve.

Mayor Kevin Hartke said at the vote that it "does not align with the city's current general plan."

Notes

The plan: a three-story, 422,877 square foot AI data center (Building A) and five research or office buildings, six buildings and about 696,874 square feet in all. The site was built in the 1990s and already includes data center space.

News accounts differ on size: ABC15 and a later KJZZ report say about 10 acres, while the minutes and application say about 40. This record follows the documents.

Related

More in Arizona

Sources

Last checked 2026-11-04.