Grid limits are shaping what gets built, and where
In several places the grid can't deliver power when a project wants it, or officials are rationing it. That helps explain the on-site generation, and it has shaped decisions on where sites may go.
The evidence
Vantage VA2: Dominion says a temporary arrangement should supply part of the campus's power by the end of 2028, so the turbines can be removed.
Price Road Innovation Campus (rejected): The city said its Price Corridor had about 80 MW available, and power for this project was expected around 2031 to 2032.
Equinix SG6: Awarded under a Singapore pilot of about 80 MW, which followed a temporary pause on new data centers.
Core Scientific Denton (CoreWeave): Denton is weighing a moratorium on new data centers. Reasons given include grid limits and water and sewer near capacity.