Operating · Documented · Location approximate
Microsoft said in October 2025 that it operates one data center in Querétaro and is building two more. Its document doesn't give an address. Reports place the operating site in Colón; that it is the same place as Ascenty 2 is not confirmed.
Microsoft. One report says Microsoft uses the Ascenty 2 building in La Esperanza, so the building's owner may be Ascenty
La Esperanza, Colón, Querétaro. The point marks the community on OpenStreetMap, not the building.
No document Footprint read gives this site's capacity or use.
Direct evaporative cooling, used less than 15% of the year, according to Microsoft. Microsoft told the BBC it uses outside air 95% of the time, per Xataka.
Private wells, according to Microsoft. Oxfam says one Microsoft campus in Querétaro is authorised to take up to 25 million litres a year. Xataka says Microsoft's Querétaro sites used 40 million litres in 2025. Those two figures are from secondary sources and aren't the same measure.
In La Esperanza a hepatitis outbreak sickened about 50 people during water cuts, and residents report blackouts, according to Xataka's summary of a New York Times investigation. Microsoft says it has no indication that its data centers contributed to outages or water shortages.
A 2022 document from Querétaro's Ministry of Sustainable Development said a Microsoft data center there did not need an environmental impact report, according to Context. Footprint has not read that document.
Gas generators: Rest of World reports that Microsoft's 2023 filings with Mexico's environment ministry said the grid wouldn't be fully available to it until mid-2027, citing CFE construction times. It reports that the ministry later approved seven gas generators to cover 70% of the site's energy, 12 hours a day, from February to July 2025. Footprint has not read the filings. Microsoft declined to say how it powers the site now.
Microsoft's document says its Mexico data centers "will be" designed to use renewable biofuel in backup generators. It does not mention gas generators.
Mexico Business News describes Microsoft's Mexico spending as cloud and AI infrastructure, which is why it is marked as an AI site. Footprint found no source naming AI work at this building.
Context reports that Microsoft uses the Ascenty 2 data centre in La Esperanza. Microsoft's own document names the Esperanza community in Colón only in connection with a training program.
Last checked 2026-11-04.