Why Texas stopped approving new data centers

Last checked 2026-11-11. Compiled with AI help and checked against the linked documents.

In November 2025, Gov. Greg Abbott said he wanted Texas to be the "epicenter of AI development," the Texas Tribune reported. Less than a year later, his office had told the state's grid operator to hold new data center connections and its environmental agency to stop issuing data center permits. Then, on November 3, 2026, he lost his race to a candidate who promised to go further.

This is how the pause was built, step by step, and what it means for the Texas sites on the map.

Four orders in four months

The first step came in June. Abbott told ERCOT, which runs most of the state's grid, and the Public Utility Commission to make data centers fully pay for the power lines and other equipment needed to serve them, according to the Tribune.

On August 3, he went further. His office directed the two agencies to "conduct a comprehensive verification and audit of all data centers advancing through ERCOT's interconnection process" before any could move ahead. Developers have to disclose any tax breaks, their projected annual and peak electricity use, any on-site power plants, their water use and cooling, how they will limit noise and light for neighbors, and who owns them. A project that doesn't meet the requirements "will be denied connection to the Texas grid," the release says.

On September 14, after as few as 28% of data centers answered a state survey on water use, Abbott told the Texas Water Development Board to penalize operators that don't report, the Tribune wrote.

The fourth, a letter on September 21, went to the Texas Commission on Environmental Quality, or TCEQ, which issues air, water and stormwater permits. "Until they do, TCEQ will issue no permits sought by data center projects," Abbott wrote, as quoted by the Tribune. The Tribune noted that this order reaches "behind the meter" data centers, which make their own power and so wouldn't otherwise be held up by the grid audit.

Did permits stop?

Not right away, according to two advocacy groups. In the weeks after September 21, FracTracker and Public Citizen counted 35 permitting actions by TCEQ for data center projects, Inside Climate News reported. They said the agency fast-tracked or assigned engineers to 14 permits, approved stormwater coverage for 11 and sent public notices for three. One of the stormwater approvals they listed was for Crusoe's Abilene campus.

Abbott's press secretary, Andrew Mahaleris, said "No permits have been approved," and that the pause covered approvals, not processing.

On October 19, TCEQ's interim executive director, Steven Schar, wrote to the governor that the agency "has paused the issuance of all permits related to the construction or development of infrastructure directly supporting data centers." Staff were screening pending applications and, "where possible," suspending authorizations that don't need a new permit. The next day a TCEQ spokesman told the Tribune the stormwater permits that had gone ahead were suspended.

Why it matters most for on-site power

Several of the largest Texas projects on the map plan to make much of their own electricity, so the state's air permits matter as much as a grid connection.

  • The Crusoe campus in Abilene being built for Microsoft has applied to TCEQ for 41 gas turbines for two buildings. The notice Footprint read was at the preliminary decision stage.
  • At the Goodnight campus in the Panhandle, Crusoe's application to TCEQ would "authorize power generation equipment for data center buildings." It was pending in the notices Footprint read.
  • At Stargate Shackelford, Oracle says the data centers run on an on-site gas microgrid, and the power company VoltaGrid has a pending TCEQ application in the same county.

Footprint hasn't found whether any of these three applications has been paused under the directive. TCEQ's letter doesn't name projects. These are plans for on-site generation, not figures for how much power any of the sites uses.

The election

Gina Hinojosa, the Democratic candidate, made data centers part of her campaign. In an October video, she pledged a moratorium, "a ban," on data center approvals until the Legislature passes laws to protect Texans, the Tribune reported after she won. She also wants operators to hire union workers, a ban on nondisclosure agreements that keep projects secret, and an end to data center tax breaks.

She has said the moratorium would apply to "any new permits," Newsweek reported. She takes office on January 19 and will work with a House led by Democrats, according to the Tribune. Until then, her pledge is a promise, not an order.

Voters were wary. A UT/Texas Politics Project poll of 1,200 registered voters in August found 41% would strongly oppose a data center in their community and 16% would somewhat oppose one, Newsweek reported. Thirty percent would support one.

What isn't known yet

The grid audit was expected to run until December, according to the Tribune. Footprint hasn't found any results, or any list of projects that passed or failed it.

None of the directives Footprint read orders a running site, like Stargate Abilene, to stop. They are about approvals for projects still seeking them. What changes is how fast new turbines, new buildings and new grid connections can be approved, and that depends on what Abbott's audit finds before January and what Hinojosa and the Legislature do after it.