OpenAI's Stargate program has several US sites at very different stages. Abilene, Texas is partly running. Others are under construction, several face lawsuits or protests, and one had cleared land but no large-scale data center construction in Epoch AI's April 2026 review. The power figures below are Epoch AI's estimates, company figures or plans, not measured use.
OpenAI Stargate Abilene is the furthest along. Epoch AI lists it as operating, with chips owned by Oracle, used by OpenAI and a campus built by Crusoe. Its April 2026 review estimated 0.3 GW running then and projected 1.2 GW by the fourth quarter of 2026.
Cleanview, citing The Information, says the site went offline for days in its first winter over power and cooling equipment.
Stargate Shackelford is under construction, a 1,200-acre Vantage campus with 10 buildings, per Epoch AI's review. Epoch AI cites Vantage as reporting 1.4 GW of computer power, and it projects 2 GW by the fourth quarter of 2028. Cleanview says more than 670 engines have been ordered for 2.58 GW of on-site generation.
Stargate Milam, near Burlington, is being built by SoftBank's SB Energy. Epoch AI lists it as under construction, and its review projects 1.2 GW by the fourth quarter of 2028.
Stargate Michigan is being developed by Related Digital on land north of Michigan Avenue. Fortune reports that Related Digital and landowners sued the township, which led to a settlement. A local outlet says the plan covers 575 acres. Attorney General Dana Nessel challenged the approval of the power contracts for the 1.4 GW facility as unlawful.
Project Jupiter is under construction, developed by STACK Infrastructure. Epoch AI says it will be powered by up to 2.45 GW of Bloom fuel cells. At least four lawsuits were pending in June 2026, and one over $165 billion in county bonds was dismissed a second time with leave to refile.
Data Center Frontier relays a Reuters report of an Oracle force-majeure notice tied to the campus. Oracle says the project remains on schedule.
Vantage Lighthouse is under construction for Oracle and OpenAI. NPR reported thousands of contractors on site, along with protests, multiple lawsuits and opponents arrested for civil disobedience.
Stargate Lordstown was the smallest and least advanced site in Epoch AI's April 2026 review, likely no more than 0.3 GW by its estimate. Epoch's directory now lists it as under construction.
Two other projects tied to the program are overseas. Stargate UAE is a planned 1 GW cluster in Abu Dhabi. In Narvik, Norway, the campus announced as Stargate Norway will be rented by Microsoft from 2027, a change from the original OpenAI plan.