Operating · Documented · Location approximate
Partly confirmed. Oracle said in September 2026 that 6 of 8 buildings had been delivered to the customer. Epoch AI estimates the last two were running by Nov. 1, 2026, but Oracle gave no date for them.
Crusoe (developer), for Oracle and OpenAI, on Lancium's campus. State air records call the site Longhorn Data Center; the federal operating permit draft names Abilene Data Center Campus Master Association
North of Abilene, Taylor County. The point marks the coordinates TCEQ gives for the Longhorn Data Center power equipment, rounded. TCEQ's address for that site is 615 FM 2404; Epoch AI lists 5502 Spinks Rd for Stargate. Footprint could not reconcile the two.
Oracle's Sept. 10, 2026 earnings call, as quoted by Epoch AI: "6 of the 8 campus buildings, representing 618 megawatts and 75% of total capacity have now been delivered to the customer". Footprint read the quote on Epoch's page, not the transcript. That is delivered IT capacity, not measured use.
A contractor, Mortenson, says it built a 200 MW, 138 kV substation for Lancium starting in 2022, and a 1 GW, 345 kV substation that was fully energized by March 10, 2026.
In early 2026 Texas Monthly reported the site was relying on its gas plant and a 200 MW substation, with batteries planned.
Grid: Oracle's fact sheet says the site "connects directly to the ERCOT grid". Lancium describes a 1.2 GW interconnect approved by ERCOT.
On-site generation: a natural gas plant at the site. Crusoe's 2024 report says "We are also building a 350 megawatt natural gas fired power plant at the site." Oracle's fact sheet says it uses GE Vernova turbines and "Ultimately, this plant will be used for backup power". TCEQ's Longhorn filing lists five Titan 350 turbines (38 MW each) and five GE LM2500 turbines (34.1 MW each) as existing, under registration 177263, issued Jan. 22, 2025.
Closed-loop, non-evaporative liquid cooling with air-cooled chillers, per Crusoe and Oracle. Epoch AI identifies 640 air-cooled chillers from imagery.
Property tax: Texas Monthly reports an 85 percent abatement approved by the city for the $3.5 billion project. KTAB reports 80 percent for Lancium once the site is fully running, and that a tenant protested the property value. Footprint has not read the agreements, and the two reports differ.
Water: developers say a closed-loop system needs a one-time fill of 8 million gallons and about 100,000 gallons a year, according to Texas Monthly. Oracle's fact sheet gives about 12,625 gallons per building per year for cooling maintenance. These are company figures, not measured use.
People in Abilene and northeast Taylor County raised concerns with Texas Monthly about power, water, noise, air pollution and road damage. The magazine reports the gas plant was authorized to emit 14 tons of air pollutants and 1.6 million tons of greenhouse gases a year; Footprint has not read that permit.
Housing: Texas Standard reported in February 2026 that the construction workforce pushed up rents in Abilene.
Name mismatch: the TCEQ documents read for this record never say Stargate, OpenAI or Oracle. Footprint links Longhorn to Stargate because the Crusoe application adds Buildings 9 and 10 to a campus already modeled with Buildings 1 to 8, in Abilene, and because Crusoe describes the same eight buildings. This is Footprint's reading.
Oracle and OpenAI's planned further expansion here ended; see the separate Crusoe Abilene expansion record.
Last checked 2026-11-04.