Data centers in Texas

See Texas on the map

234 sites · 16 researched · 11 local bans or limits in effect · 5 proposed

Temporary data center bans are often called moratoriums.

Local bans and limits in effect

Proposed bans and limits

Failed, retracted or expired (2)

Researched sites

Listed sites, largest first

Show all 218

Upcoming dates

  • As early as Dec. 1, 2026: Denton vote on a data center moratorium
  • Expected by Dec. 7, 2026: Texas regulators due to rule on the gas plant for Meta's El Paso campus
  • By Dec. 31, 2026: Deadline for Texas Tech's go-ahead on Project Matador
  • June 28, 2027: First Anthropic block at Riot Corsicana targeted to start
  • Mid-2027: First Microsoft building in Abilene due to be energized, Crusoe says
  • Q2 2027: Helios Phase II rent due to start, Galaxy says
  • No date found: TCEQ decision on Crusoe's Abilene gas turbines
  • No date found: TCEQ decision on the Goodnight gas plant
  • No date found: TCEQ decision on VoltaGrid's Shackelford County plant

Articles

In the news

  • OpenAI Stargate Abilene: Operating; chips owned by Oracle and used by OpenAI, built by Crusoe. Epoch AI's April 2026 review estimated 0.3 GW running and 1.2 GW projected by Q4 2026 (estimates), with four of eight buildings operating. Crusoe filed for a 360 MW on-site power plant here, per Cleanview (on-site generation). The site went offline for days in its first winter over power and cooling equipment, per Cleanview citing The Information. 618 MW across six buildings is the largest dated delivered figure, per this guide (delivered capacity). source 1 · source 2 · source 3 · source 4
  • Blueprint Taylor data center: Attorney General Paxton is investigating whether a 1999 deed restricting the land to parkland was properly released. Residents sued developer NCP Travis TPP Project, LLC, and a state district judge dismissed the suit for lack of standing. Planned at 135,000 square feet by Blueprint Data Centers on about 87 acres, per CNN. source 1 · source 2 · source 3
  • OpenAI Stargate Shackelford: Under construction; a 1,200-acre campus by Vantage with 10 buildings, per Epoch AI's April 2026 review. Vantage reports 1.4 GW of IT power (company figure); Epoch AI projects 2 GW by Q4 2028 in that review. More than 670 reciprocating engines ordered for 2.58 GW of on-site generation, per Cleanview. source 1 · source 2
  • OpenAI Stargate Milam: Under construction near Burlington; chips owned by SoftBank and used by OpenAI, per Epoch AI. Built by SoftBank's SB Energy; 1.2 GW projected by Q4 2028 (Epoch AI estimate). 857 MW of IT power projected by Q4 2028 (Epoch AI estimate). OpenAI says it chose SoftBank's SB Energy to build and operate the site and signed a 1.2 GW data center lease for the initial buildout (planned size), and that the partners plan to build new generation for its energy needs. The state construction filing for Phase 1, "Freebird", lists a single-story, 548,950-square-foot building with four data halls on County Road 133 in Burlington, an estimated $470 million, OpenAI as tenant, and work from Oct. 20, 2025 to Oct. 15, 2026. Footprint hasn't found a report that it is running. source 1 · source 2 · source 3 · source 4
  • Project Matador: About 12 miles northeast of Amarillo on 7,570 acres, with Fermi holding a 99-year ground lease on 5,855 acres, per Lone Star Left. Fermi describes an 11 GW gas-bridged nuclear build (planned on-site generation), with 2.0 GW of combined-cycle gas equipment secured or under letter of intent in September 2025. Carson County approved a 10-year property tax abatement, per Lone Star Left, a critical source. On Nov. 12, 2026, Fermi said an undisclosed investment-grade hyperscaler is working toward an initial 600 MW of planned capacity there from 2027, with a $200 million prepayment ahead of a lease that isn't signed yet, and that TensorWave's lease has been terminated, per its SEC filing. source 1 · source 2 · source 3
  • Meta El Paso: Meta is building a $10 billion, 1 GW data center (planned capacity) in northeast El Paso; it was under construction in September 2026. El Paso Electric seeks a 366 MW gas plant called McCloud, with 813 modular generators at about $499 million (on-site generation). State judges found the utility considered no alternatives and recommended approval only if ratepayers are not charged; over 1,000 people sent opposing comments. Groundbreaking was October 2025; the data center would be El Paso's largest power user. source 1 · source 2
  • Project Patriot: Hood County officials first heard of it in July 2025 as a secret pitch promising 60 permanent jobs. A 2,084-acre proposal; recall petitions against Granbury's mayor and council were in dispute. source 1 · source 2
  • Barber Lake: Under construction; chips owned by Cipher and used by Anthropic, with 207 MW of IT power projected by Q2 2027 (Epoch AI estimate). source 1
  • Crusoe Abilene expansion: Under construction; chips owned and likely used by Microsoft, per Epoch AI. Projected 672 MW of IT power by Q4 2027 (Epoch AI estimate). source 1
  • Goodnight campus: Under construction; Google is only a possible owner per Epoch AI, with 1,006 MW of IT power projected by Q4 2027 (estimate). source 1
  • Comanche Circle: Commissioners voted 3-1 to approve the concept plan for the 2,100-acre campus after a shouting match; the project moves to the next review stage. Needs a one-time 95 million gallon fill, then 150,000 gallons a day; with two smaller sites could use up to 3 GW (developer figure). Listed at 3,200 MW in a Cleanview-based analysis (planned capacity). source 1 · source 2 · source 3
  • GW Ranch: TCEQ issued an air permit for up to 7.65 GW of gas generation (permitted on-site generation), about 17 miles north of Fort Stockton. Developer expects to supply power in the first half of 2027. source 1

Researched sites are Footprint's records. Listed sites and local rules: data provided by FracTracker Alliance (2026), accessed via fractracker.org/data-centers, shown as published and not reviewed by Footprint. These lists don't cover every data center.