Proposed · Documented · Location approximate
Site work is done or underway, but Fermi's lease bars vertical data center construction until Texas Tech issues a notice to proceed, due by Dec. 31, 2026. Fermi's Nov. 12, 2026 results say the two are still working on those conditions. Fermi paused construction in early 2026 while waiting for an air permit.
Fermi Inc. (Fermi America), on land leased from the Texas Tech University System. Customer: an undisclosed investment-grade hyperscaler, with no lease signed yet. TensorWave's lease was terminated
Carson County, near the Pantex plant and Amarillo. The point marks Pantex (OpenStreetMap), not the site.
New customer: Fermi says an undisclosed investment-grade hyperscaler is working toward an initial 600 MW of power capacity at the site, beginning in 2027. It has agreed to a $200 million prepayment and a $15 million early construction and site development agreement, ahead of a lease, which hasn't been signed. Fermi says the customer plans to build its own data centers. 600 MW is planned capacity, not use.
Fermi's filing describes about 11 GW of planned private-grid power, expandable to about 17 GW if permits and land come through. Those are plans. No data center is running.
TensorWave lease: the filing read in October described 222 MW of total power, 156 MW of critical IT load and an option up to 650 MW. Fermi's Nov. 12, 2026 results say TensorWave's lease and services agreement, signed in August 2026, has been terminated, along with an AMD credit support agreement tied to it.
Fermi plans four reactors, one each year from 2033 to 2036. These are company plans.
On-site generation (planned): Fermi's filing describes on-site natural gas generation with supplemental grid power and batteries.
Fermi's filing lists six groundwater leases on about 5,227 acres in Carson County through its Fermi Water subsidiary.
Texas Monthly reported considerable opposition in Amarillo to the project.
An unnamed first tenant ended a $150 million construction funding deal in December 2025, according to ABC 7 Amarillo, citing a security filing.
Fermi's filing notes the termination of its former CEO and the resignation of its former CFO.
DCD reports about 6 GW of the plan is permitted, and Fermi's fact sheet refers to expansion beyond about 6 GW. Footprint has not read the permit.
Why this is marked as AI: Fermi's filing describes AI data center infrastructure.
KFDA reported in February 2026 that three million square feet had been cleared near Pantex and construction was paused.
Fermi's Nov. 12, 2026 release says it and Texas Tech are working on "the conditions under the land lease that precede vertical construction." It doesn't say a notice to proceed has been issued.
Fermi's third-quarter net loss was $141.6 million, and it reports nearly $1.7 billion invested in the buildout so far.