Operating · Documented · Location approximate
Operating as a bitcoin mine and data center. AMD's first 25 MW was delivered by May 2026. Anthropic's 191 MW is planned for December 2027 to June 2028.
Riot Platforms. Data center tenants: AMD and Anthropic PBC
Rockdale, Milam County. The point marks the town, not the site. Footprint did not find a primary document with the street address.
AMD lease: 50 MW of critical IT load, with possible expansion to 200 MW. Anthropic lease: 191 MW for 20 years.
Grid: Riot's filing says the PUCT, ERCOT and Oncor oversee power supply and delivery at its Texas sites. It has had curtailments at their instruction.
Two buildings with immersion cooling (200 MW) and five air-cooled (500 MW), according to DCD. This describes the mining buildings before conversion.
Anthropic PBC is named as the tenant in Riot's Nov. 4, 2026 filing, which calls it the "Frontier AI Lab". Anthropic makes Claude, the AI used to compile these records.
Marked as AI because of the AMD and Anthropic leases, though the site began as a bitcoin mine.
Last checked 2026-11-04.