How much electricity does a data center actually use?

Last checked 2026-11-05. Compiled with AI help and checked against the linked documents.

Often the public can't tell. In Footprint's records, sources give planned capacity and grid requests far more often than what a site draws. Of the 35 operating sites among the 66 Footprint has researched, two have a company-reported electricity figure, and none states it in megawatts. These are selected sites, not a representative sample.

Three numbers that get mixed up

Actual electricity use is what a site really draws. It's the rarest of the three in Footprint's records.

Design capacity is what a site or campus is built or planned to handle. STACK NVA02 in Manassas, Virginia lists 420 MW of "critical capacity" for a 10-building campus. Epoch AI estimates about 85 MW of computer power there now, because only part of it is built.

Requested grid capacity is what a site has asked a utility or grid operator to supply. Colossus 2 in Memphis shows how fluid that can be. MLGW said in May 2025 that the initial request was 260 MW, that options up to 1.1 GW had been discussed, and that no final request had been made.

One site, several figures

OpenAI Stargate Abilene in Texas has several of these at once, and none is measured use:

  • 1,200 MW: Crusoe's total capacity for the first eight buildings.
  • 1.2 GW: the grid connection Lancium says ERCOT has approved.
  • 618 MW: computer capacity delivered in six of the eight buildings, from Oracle's September 2026 earnings call, as quoted by Epoch AI.
  • 824 MW: Epoch AI's own estimate of computer power there now.

The few measurements

Apple publishes one. Its environmental report gives 563 million kWh for its Mesa, Arizona site in fiscal 2025. Spread evenly over the 8,760 hours in a year, that's about 64 MW. That average is Footprint's arithmetic, and it says nothing about peaks.

Meta reports 24,657 MWh at Mesa in 2024, but that was before the site went online, so it says little about full use.

Other figures can look like measurements but aren't. MLGW said 150 MW was reaching Colossus 1 in May 2025, which is supply on one date. xAI's sworn declaration gives the expected power draw of the computer chips at Colossus 2 and the Stateline Road site, but the number is blacked out in the public copy. These examples are also in the finding on actual use.

What outside estimates can and can't tell you

Where nothing is published, researchers estimate. Epoch AI estimates computer power, mostly from satellite images. It leaves out cooling and other equipment, and Epoch says 80% of its estimates are within a factor of 1.4. That's useful for scale, but it isn't a meter reading.

How to read a number you come across

  • Is it measured, planned or requested? Words like "capacity," "campus" and "up to" usually mean it isn't measured.
  • Does it cover the whole site? Computer power leaves out cooling and other equipment.
  • Which part of the project? A figure may cover one building, one phase or a full build-out.
  • What date is it from? Supply on one day doesn't tell you about the rest of the year.
  • Who said it? A company, a utility, a court filing and a researcher's estimate carry different weight.

Explore the map to see which of these figures exist for each site. Records keep them separate and label estimates.