Colossus 2

Operating · Documented · Location confirmed

Operator

xAI (SpaceXAI)

Location

5420 Tulane Road, Memphis (Whitehaven), TN 38109

Whitehaven, Shelby County, Tennessee, near the Mississippi state line

Power

  • Requested grid capacity: 260 MW
  • Estimated electrical use: 946 MW (Epoch AI estimate)

xAI's sworn court declaration gives the expected power draw of the GPUs at this site and the Stateline Road site, but that figure is blacked out in the public copy.

SpaceX's SEC filing gives "compute power" for Colossus II, a name it uses for the Tulane Road and Stateline Road sites together: about 210 MW for the first cluster and 220 MW for the second, with over 400 MW more in the next phase. It does not split these by site, and they are not total site use.

  • 946 MW IT power now, Epoch AI estimate
  • 1,531 MW IT power by Q1 2027, Epoch AI projection

Power connection

Powered by the Stanton Road gas turbines, 2875 Stanton Road, Southaven. xAI's sworn declaration: "The Stanton Road site supplies power to the Tulane Road and Stateline facilities." As of June 2026, xAI's staff said the temporary turbines there were the only available power source for these two sites. SpaceX's SEC filing says Colossus II "is capable of operating entirely by our self-built behind-the-meter gigawatt-scale natural gas power plant", with more grid capacity to be added over time.

Cooling

Direct-to-chip cooling, per SpaceX's SEC filing. Epoch AI also identifies air-cooled chillers from satellite imagery.

Water

MLGW public water, from an existing main. MLGW said in May 2025 that xAI had not requested more water service and was not using significant water here. That predates the site's start-up, and Footprint found no later figure.

Community

Residents of Whitehaven and neighboring Southaven have spoken out about turbine noise and air pollution at state hearings. Young, Gifted & Green and the Safe and Sound Coalition are among the groups opposing the power plant.

An NAACP Clean Air Act lawsuit over the turbines powering this site is under way in federal court in Mississippi. A judge denied xAI's motion to dismiss on Oct. 30, 2026. The case has not decided whether the companies broke the law.

Mississippi's Permit Board voted Nov. 10, 2026 to stand by the air permit for the 41-turbine Stanton Road plant that would power this site, after a two-day evidentiary hearing, DeSoto County News reports. Commissioner Andy Gipson cast the only no vote. Public comment wasn't taken at the formal hearing. Opponents could ask a court to review the decision.

Residents near the xAI campus sued over turbine noise, NPR reported in September 2026. NPR describes about 60 turbines and says xAI promised in July to replace them within a year. NPR names the campus, not a building.

Notes

In May 2026 SpaceX entered cloud services agreements giving Anthropic access to computing capacity across Colossus and Colossus II, according to its SEC filing. xAI's sworn declaration also names Cursor and Google as users of the Tulane Road and Stateline Road sites. Anthropic makes Claude, the AI used to compile these records.