Operating · Documented · Location approximate
Apple
3740 S. Signal Butte Rd, Mesa, Arizona (from a 2014 federal notice; the Census geocoder did not match it)
Southeast Mesa, 83.17 acres per the 2014 notice. The point marks Signal Butte Road south of Elliot Road, estimated because the address did not geocode.
Apple reports 563 million kWh of electricity at Mesa in fiscal 2025, up from 530 million in fiscal 2024. Spread evenly over a year, 563 million kWh is about 64 MW (Footprint arithmetic). This is measured use reported by Apple, but Apple doesn't state it in MW, so it isn't in the power field.
Apple says it partnered with Salt River Project on the 50 MW Bonnybrooke solar project to support the site. That is a clean-energy arrangement, not a documented physical link, so it isn't shown as a connection.
On-site generation: solar on parking canopies and ground arrays, 4.67 MW total, operating since February 2019, per Apple.
No Mesa-only figure. Apple's report lists 335 million gallons of 2025 freshwater withdrawals for the Lower Colorado River Basin region, naming "Mesa Data Center, San Diego" as major sites and covering all its corporate facilities there. The supplier isn't named. Footprint reading of a table in a PDF: the 335 sits across rows.
Apple calls it its global command data center. Epoch AI's directory has no entry for it.
Apple says the site came online in 2016. The 2014 notice is from before that, when Apple sought foreign-trade status for the same address in Mesa.
Last checked 2026-11-04.