"Clean energy" often means a contract, not the power running the site
Companies describe buying or matching renewable power. Those are real purchases, but the documents we read don't show that power physically reaching these sites, so Footprint doesn't draw a connection.
Google Mesa data center: A 2024 report says Google signed for 434 MW of renewable capacity tied to the Mesa project.
Goodnight campus: Here there is a documented wind connection. But Crusoe's release calls the site clean energy and doesn't mention the gas plant its own company applied for.