Operating · Documented · Location approximate
Microsoft says it operates data centers in El Mirage and is building new ones in the area. Which buildings are finished isn't in the sources read.
Microsoft
El Mirage, Maricopa County. The point marks Dysart Road near Northern, beside the land Microsoft bought in 2024. No document read gives the campus's own address.
Microsoft says it covers its Arizona electricity through a power purchase agreement with the Sun Streams 2 solar project. That is a contract, not a documented physical connection.
Microsoft's October 2025 fact sheet says existing Arizona facilities use direct evaporative cooling, which "uses water for cooling less than 40% of the year," and future ones will use air-cooled chillers. The sheet covers Arizona as a whole, not this campus alone.
Microsoft says it buys water in Arizona from EPCOR and the City of Goodyear, without saying which site uses which. No site figure found.
A major Microsoft campus. Epoch AI's directory lists Microsoft's Goodyear site but not El Mirage.
Microsoft announced in June 2021 that its El Mirage and Goodyear data centers were running, as part of its West US 3 cloud region.
Microsoft paid for 282.78 acres at the northwest and northeast corners of N Dysart Rd and W Northern Pkwy, next to its existing campus, in 2024. Two eastern parcels were proposed for conversion from warehouse use to a data center, according to planning documents cited in the report.
Last checked 2026-11-04.