Under construction · Documented · Location approximate
Crusoe said on Sept. 28, 2026 the campus is under construction with more than 5,500 workers a day. The gas plant air permit was pending in the notices Footprint read; no final decision found.
Crusoe (developer), for Google. Tax deal holder: GN DC1, LLC. Air permit applicant: Crusoe Energy Systems LLC
10001 Lima Road, Claude, TX 79019
Armstrong County, east of Amarillo. The Census geocoder could not place the address, so the point marks TCEQ's coordinates, rounded.
TCEQ's summary lists proposed emissions of 4,594,980 tons a year of CO2 equivalent and 552.1 tons of NOx. The summary says these may change during review.
News reports, citing Cleanview's reading of the application, describe a 933 MW gas plant that would run apart from the grid and power at least two buildings. Footprint has not read the application itself.
Crusoe's September 2026 release calls this "clean energy" and mentions only the wind farms. It does not mention the gas plant its own company applied for.
Wind: Crusoe says "The campus has a direct connection to Serena's adjacent Goodnight 1 (265.5 MW) wind farm", with Goodnight 2 (265.5 MW) under construction, and that surplus wind power goes to the grid.
On-site generation (proposed): TCEQ application 182880 from Crusoe Energy Systems says the Goodnight Data Center "will generate electricity" and that the permit would "authorize power generation equipment for data center buildings".
Crusoe says closed-loop, non-evaporative liquid cooling, limiting water mainly to domestic uses such as kitchens. Google's statement to FOX 7 says closed-loop air-cooled.
Armstrong County approved abatement agreements in November 2024, and amended ones in 2025. The amended agreement defines abatement as full exemption from property taxes on covered property, for up to 10 years per period.
Grid operator conflict: one report says the Goodnight gas plant would not connect to the grid and that the area's grid is the Southwest Power Pool, not ERCOT. Footprint has no primary document on this.
Crusoe's release calls this "Google's data center campus". Epoch AI's list still marks Google as speculative.
State permit pause: Gov. Greg Abbott told TCEQ on Sept. 21, 2026 to issue no permits sought by data center projects until ERCOT and Texas Water Development Board audits are done. TCEQ wrote on Oct. 19 that it had paused issuing all permits for infrastructure directly supporting data centers and was screening pending applications. Footprint hasn't found whether Crusoe's gas plant application 182880 has been paused under the directive.
Last checked 2026-11-11.