Crusoe Abilene expansion (Microsoft)

Under construction · Documented · Location confirmed

Crusoe said land clearing was underway in March 2026. Air permit status: TCEQ has published a notice of preliminary decision. Footprint did not find a final permit decision.

Operator

Crusoe (developer), for Microsoft. Air permit applicant: Crusoe Energy Systems LLC (Crusoe Technologies LLC on the later TCEQ notice)

Location

615 Farm-to-Market Road 2404, Abilene, TX 79601

Next to the Stargate buildings, Taylor County. The point comes from the address TCEQ gives for Buildings 9 and 10, not the buildings' outline.

Power

  • Design capacity: 900 MW

Crusoe's figure for the whole Abilene site, including this expansion, is about 2.1 GW projected.

TCEQ's plain language summary lists proposed yearly emissions including 760.33 tons of NOx, 870.07 tons of CO and 49.77 tons of hazardous air pollutants. The summary says these may change during review.

  • 672 MW Projected IT power, Epoch AI estimate

Power connection

On-site generation: Crusoe says a 900 MW "behind-the-meter" on-site plant with batteries provides dedicated energy. The TCEQ application for Buildings 9 and 10 adds 41 GE LM2500/Aero DT35 natural gas turbines, with diesel black-start and backup generators, and says the facility's purpose is "to generate power for onsite use for data centers and computing".

Cooling

Closed-loop, non-evaporative liquid cooling, per Crusoe.

Notes

Name check: TCEQ's filing says Buildings 9 and 10 and does not name Microsoft. Crusoe's release says two new buildings and an on-site plant next to the existing campus and does not give a permit number. Footprint treats them as the same project because the two descriptions match, and Epoch AI ties them together.

Oracle and OpenAI were earlier expected to take this capacity, then dropped the plan, according to DCD and The Register. Bloomberg's original report was blocked, so Footprint did not read it.

Crusoe expects the first building to be energized in mid-2027. That is the company's forecast. Epoch AI projects Building 1 operating in September 2027.

State permit pause: Gov. Greg Abbott told TCEQ on Sept. 21, 2026 to issue no permits sought by data center projects until ERCOT and Texas Water Development Board audits are done. TCEQ wrote on Oct. 19 that it had paused issuing all permits for infrastructure directly supporting data centers and was screening pending applications. Footprint hasn't found whether air permit 182126 has been paused under the directive.

Related

More in Texas

Sources

Last checked 2026-11-11.