Under construction · Documented · Location approximate
Meta broke ground in October 2025. In July 2026 Meta and BlackRock called the campus under construction and said capacity should start coming online in 2028. The state filing lists completion in February 2029.
Meta. A venture 80% owned by funds managed by BlackRock and 20% by Meta owns the campus, and Meta leases all of it. The state construction filing lists Wurldwide LLC as owner.
Northeast El Paso, between Stan Roberts Sr. Ave. and State Line Road, per El Paso Matters. The state filing gives 7001 Stan Roberts Sr. Ave., El Paso, TX 79934, but the point is FracTracker's location for this listing, rounded, not a geocoded address.
Proposed gas plant, not approved: El Paso Electric's McCloud Generation Facility, 366 MW of natural gas generation from 813 modular generators of 450 kW each, estimated at $499 million, to serve the Meta data center. Inside Climate News reports it would supply Meta only for the first five years, with Meta paying its costs then, before connecting to the wider grid. In September 2026, state administrative law judges recommended approval only if other customers are not charged for it, and denial otherwise. The Public Utility Commission had not voted in the sources read. Footprint has not read the utility's filing.
Meta says it paid El Paso Electric for new grid infrastructure, including transmission lines and substations, and that the data center's electricity use "will be matched with 100% clean and renewable energy."
The state filing lists 5 owner substations among the 12 new buildings and site work.
El Paso Electric says the gas plant was developed in response to Meta's requests to "accelerate expansion of its original load requirements by 2027," El Paso Matters reports. No megawatt figure for the data center's own load was given in the sources read.
Grid: Meta says that through an agreement with El Paso Electric it paid for new grid infrastructure, including transmission lines and substations. It does not describe the connection further.
Closed-loop, liquid-cooled. Meta says the system "will use zero water for a majority of the year."
El Paso Water estimates the data center will use an average of 400,000 gallons a day, El Paso Matters reports. That is the city utility's estimate, not a measurement. Meta says it will restore 200% of the water the site consumes to local watersheds.
Gas plant: the Sembrando Esperanza Coalition sent comments from more than 1,000 people opposing El Paso Electric's application, Inside Climate News reports. The judges found the utility did not adequately consider alternatives and did not seek bids, writing that "The selection of the Project was driven by Wurldwide's prescribed timeline and preferences."
Ratepayers: on Sept. 28, 2026, El Paso City Council authorized the city attorney to keep negotiating with El Paso Electric for a "full hold harmless" for ratepayers on the plant's costs, KVIA reports. The utility's CEO said costs of serving these customers should be "appropriately assigned to them." KVIA reports a final commission order is expected by Dec. 7, 2026.
Tax break: the city and county approved an 80% property tax break for decades, and the city agreed to $12.5 million for road repairs around the site. The agreement requires Meta to hire only 50 workers, El Paso Matters reports.
Emissions: utility filings and Enchanted Rock figures put the gas plant at about 117 metric tons of nitrogen oxides, 2,700 metric tons of carbon monoxide and 42 metric tons of particulate matter a year, El Paso Matters reports. The plant is not approved.
Meta says the investment grew from more than $1.5 billion to more than $10 billion, with more than 4,000 construction jobs at peak and more than 300 operating jobs. Meta and BlackRock put total development costs at about $14 billion.
Lease: Meta will be the sole initial occupant, with a four-year initial lease term and four extension options for up to 20 years, and provides residual value guarantees, per Meta and BlackRock.
State filing: TDLR project TABS2026017750, "Project Seafox", covers a hyperscale campus of 12 new buildings, 5 owner substations and site work on about 600 acres, 25,943,100 square feet in all, at an estimated $289 million. It lists work from Nov. 1, 2025 to Feb. 28, 2029. The cost in this filing is far below Meta's total investment figure.
Why this is marked as AI: Meta describes it as an AI-optimized data center, and Meta and BlackRock put it at 1 GW.
Last checked 2026-11-23.