Operating · Documented · Location confirmed
Operating as a bitcoin mine, up to about 400 MW. The data center lease only took effect on Nov. 4, 2026; that part has not been delivered. A state filing shows a data center building, Project Ditto, registered from April 2026.
Riot Platforms. Data center tenant: Anthropic PBC
6980 FM 709, Corsicana, TX 75110
Navarro County, about seven miles outside Corsicana. The point is the address, not the campus outline.
Currently equipped for up to about 400 MW for bitcoin mining, per Riot's filing.
Lease phases: 400 MW targeted to start June 28 to Sept. 11, 2027; 200 MW Dec. 24, 2027 to Jan. 28, 2028; 310 MW July 30, 2028. These are Riot's targets.
Grid: Riot's filing says the PUCT, ERCOT and Oncor oversee power supply and delivery at its Texas sites. It says Corsicana is in an ERCOT large-load group whose use could be capped or curtailed, and that ERCOT has not activated a mitigation plan for this group.
Riot's filing mentions contracts for water supply infrastructure for the facility and does not name the source.
At the 2022 groundbreaking, a group called Concerned Citizens of Navarro County opposed the project, NBC 5 reported.
Anthropic PBC is named as the tenant in Riot's Nov. 4, 2026 filing, which calls it the "Frontier AI Lab". Anthropic makes Claude, the AI used to compile these records.
Marked as AI because of the lease, though the site began as a bitcoin mine. Riot leases land, powered pads and related infrastructure, and the tenant develops and operates the data center.
15-year term from Riot's filing: base rent of $130 per kilowatt of critical IT load a month, rising 3 percent a year, with the tenant paying electricity.
Last checked 2026-11-04.