Under construction · Documented · Location approximate
Construction began in December 2025. Vantage's plan in the state's review has Project 1 finishing in the third quarter of 2028 and Project 2 in the fourth. Vantage told regulators the campus will not be fully operational without a transmission project that is not yet approved.
Vantage Data Centers (owner, through VDC Wisco Realty Investments 1, LLC), for Oracle and OpenAI. The utility's end-use customer is Oracle America Cloud Services LLC. Cloverleaf Infrastructure first assembled the land
East of Ozaukee Trail, south of Dixie Road/County Highway P and west of I-43, about 1 mile inland from Lake Michigan, Port Washington, Ozaukee County, Wisconsin. The point is the coordinate the state air permit record gives for the facility, rounded; that record gives no street number.
Vantage told the DNR it contracted with We Energies for 1.85 GW from new and existing sources, split as gas 840 MW, solar 386 MW, batteries 354 MW, nuclear 236 MW and wind 36 MW. The DNR's report is not consistent on this: it also says 1.3 GW plus 55 MW, and gives nuclear as both 236 and 354 MW.
The DNR says 1.3 GW would equal a 17% increase in Wisconsin's electricity use.
The Daily Reporter gives 902 MW for the campus, and the announcement of the project says "close to a gigawatt of AI capacity". Neither says what the figure measures against the 1.3 GW above.
Oracle's service from We Energies is currently planned to start June 1, 2027, according to ATC's application. ATC says transmission construction would take about 17 months after approval. The refiled application was found incomplete on Oct. 19, 2026.
Cloverleaf's earlier plan was for 3.5 GW on about 1,900 acres. Vantage told the DNR it has no current plans for data centers on the 972 acres north of this campus.
Grid, planned and not approved: ATC proposes two new double-circuit 345 kV lines from a new Decker Substation on Vantage's property, plus rebuilt lines and new substations across several counties. The first application, docket 137-CE-221, was closed in September 2026. The refiled one, docket 137-CE-229, was found incomplete on Oct. 19, 2026.
On-site backup: up to 45 diesel emergency generators totaling 87 MW, under DNR air permits 25-MIN-094 and 24618528A-F01, issued June 12, 2026.
Closed-loop system with dry coolers, using a water and antifreeze mix. The DNR says it would use no water in normal operation and takes more electricity than an open system. Vantage's sustainability plan targets a PUE of 1.18.
City of Port Washington public water, with no direct connection to Lake Michigan, according to the city. The city puts use at about what 65 homes use. That is a planning figure, not measured use.
Transmission lines drew the largest fight. The Public Service Commission received 2,768 comments before revoking its finding that ATC's first application was complete. It said the decision was not a ruling on the project's merits. The Responsible Energy Alliance, whose leaders include local residents, asked for the revocation.
ATC's estimate is $2.48 billion to $2.72 billion, depending on route. Of that, $1.10 billion is a device to steady the data center's load swings, a 600 MW E-STATCOM. ATC says Oracle pays for that device and nearly all the rest, apart from a small regionally shared part.
Port Washington's mayor and council voted in October 2025 to oppose ATC's preferred route. Vantage later backed the $1.64 billion alternative. ATC said at the time its preferred route costs ratepayers less and uses existing corridors.
Oracle sued state regulators in June 2026 over a rule requiring customers rated below A- to post collateral, which could cost it over $100 million a year. It moved to drop the suit in August 2026.
Tax financing: the city says Vantage pays about $175 million for infrastructure up front and is repaid through a tax district. Great Lakes Neighbors United, a group opposed to the project, sued and said repayment with interest could top $458 million. A judge's oral ruling dismissed the suit in September 2026; the order still needed signing.
About 66% of voters approved an April 2026 measure requiring votes on future tax districts of $10 million or more. It does not change this project's district. A judge dismissed a business group's challenge in October 2026, and the group says it may go to a higher court.
Residents filed paperwork in late 2025 to recall Mayor Ted Neitzke, saying he did not inform the public about the project, according to a report citing the Milwaukee Journal Sentinel.
The city says the development agreement protects residents from project costs. We Energies says no costs to serve data centers will shift to other customers. Clean Wisconsin says energy infrastructure is the top concern for neighbors and environmental groups.
Building the campus would fill 4.7 acres of wetland, according to the DNR, which granted state wetland exemptions in December 2025.
NPR reported angry protests, multiple lawsuits and opponents arrested for civil disobedience in October 2026.
Four buildings, two of about 719,000 and two of about 560,000 square feet, on 672 acres. Vantage owns or has under contract 1,644 acres in all.
Vantage's investment was first set at $8 billion or more in the development agreement approved in August 2025. It was later reported as $15 billion.
OpenAI, Oracle and Vantage announced the site in October 2025 as part of Stargate.
Last checked 2026-11-05.