The Digital Gateway: a 27-hour hearing, undone by a public notice

Last checked 2026-11-05. Compiled with AI help and checked against the linked documents.

Shortly after noon on Monday, November 20, 2023, the clerk of Prince William County's Board of Supervisors emailed The Washington Post an ad for a public hearing. Two hours later, the Post replied with a price: $7,509.48. "Saved ads will not run unless they are scheduled and submitted," the email said. Two minutes after that, another email said the clerk had to confirm by 3 p.m. the next day. According to the court's later account, the clerk didn't respond by the deadline, and the ad didn't run on November 28.

The ad was for the hearing on the Prince William Digital Gateway, reported as planned to be the world's largest data center complex. It had been years in the making.

The years before

Data centers were already on the county's list of targeted industries. On July 20, 2021, the board started a change to its long-range land plan along Pageland Lane, next to Manassas National Battlefield Park.

Homeowners on the road organized the effort, bundling their properties. By 2023, the Prince William Times counted 102 landowners under contract, in a deal estimated at more than $1 billion. Regional labor unions backed it. Neighbors, the National Park Service and conservation groups opposed it.

In January 2022, more than 100 people signed up to speak at one meeting. "It's a total and complete change of the character," opponent Kathy Kulick said. Owners ready to sell said the tax benefits were worth it.

The board adopted the plan change on November 1, 2022. Residents sued, and in May 2023 a judge dismissed one case, calling the plan "an advisory document" that, unlike a rezoning, didn't determine land use.

County finance officials estimated $24.7 billion in investment and $400.5 million a year in tax revenue. Compass said its part could need as much as 1.7 GW of electric capacity, The Washington Post reported. That's a planned figure, for a project never built. The companies also offered about 270 acres of public open space.

County planners faulted the applications for lacking building locations. On November 8, 2023, the Planning Commission, an advisory body, recommended denial. The board's hearing was set for December 12.

Twenty-seven hours

When the first ad didn't run, the opinion says, the board ran three others, on December 2, 5 and 9.

The day before the hearing, a lawyer for residents wrote to complain about the advertising and threatened legal action. At the hearing, Supervisor Robert Weir moved to wait "until such date as a proper public notice has issued." The motion failed 5-3.

Then came six hours of presentations and more than 17 hours of public comment. A motion to deny failed 4-4. A motion to approve passed 4-3, with one abstention. The board split largely by party. It adjourned at 1:14 p.m. on December 13, 27 hours after it began.

The notice

Two groups of plaintiffs sued within 30 days. The opinion traces what followed. One judge, Tracy Hudson, dismissed one case in 2024, reasoning the newspaper had failed to publish. Another, Kimberly Irving, held a five-day trial in June 2025 and found the opposite: the board, not the Post, was at fault. She also found the ordinances weren't available to examine until December 7, after the first two ads had run. She declared the rezonings void.

On March 31, 2026, Virginia's Court of Appeals agreed. Judge Stuart Raphael wrote that Irving's finding was "well-supported by credible evidence." Because the board "violated the advertising rules," the court held the rezonings void from the start. The ruling rested on the advertising rules. Other claims in the case were never reached.

The end of the case

On April 14, the board voted unanimously to drop its defense, after spending about $1.7 million. "This litigation should never have happened," said Mac Haddow, president of the Oak Valley Homeowners Association. David Duncan of the American Battlefield Trust, which also sued, called the rezonings "illegal."

Compass also withdrew. On July 2, QTS withdrew too, saying it had decided to end the project. Its notice said the plan was approved "following a rigorous process" and would have brought "tens of billions of dollars in capital investment" and "thousands of long-term jobs."

What remains

The county's page says a July 29 court order returned the land to its earlier zoning, and that properties will be reassessed for tax. It also says the 2022 plan change remains in place, and that any new effort would go through the normal rezoning process.

Footprint hasn't found a new application for this land, or a report on what became of the landowners' sale contracts. Sizes differ too: the three rezonings total 1,760 acres, by Footprint's addition, while news reports say about 2,000 to 2,100.

Other local fights have ended differently.