Cancelled · Documented · Location approximate
QTS and Compass Datacenters (developers)
Along Pageland Lane near Gainesville, next to Manassas National Battlefield Park, Prince William County
Reported as planned to be the world's largest data center complex. Opponents raised harm to the watershed, wildlife and the battlefield park's historic feel. Oak Valley Homeowners Association and the American Battlefield Trust led the challenges.
Virginia's Court of Appeals held the three rezonings void from the start on March 31, 2026, over defective public notice. As many as 37 data centers were planned.
QTS withdrew its final appeal in July 2026, saying it had decided to end the project. Compass and the county had already withdrawn.
Sizes differ: the three rezonings in the opinion total 1,760 acres (Footprint arithmetic), while news reports say about 2,000 to 2,100 acres.
Last checked 2026-11-04.