Under construction · Documented · Location approximate
The neighbours' filing says works were practically finished in July 2026, according to El Observador. Google's locations page says this "will be" its second data center in the region. Footprint found no statement that it has started operating.
Google, through Eleanor Applications S.R.L.
Parque de las Ciencias, Ruta 101 km 23.500, Canelones (32.5-hectare plot within the park)
Canelones, Uruguay. Filings say Ciudad de la Costa and Barros Blancos, and OpenStreetMap places the park in Nicolich. The point marks the park on OpenStreetMap, not the plot.
The ministry's final report says maximum energy use at full build will be under 560 GWh a year, with an initial UTE agreement for up to 420 GWh a year. These are energy figures, not megawatts. The report also says backup generation capacity is above 10 MW and describes generators of 2,750 kW and 1,000 kW.
Grid: UTE's national grid through a 150 kV UTE switching station and Google's own substation on the site's east side, per the project document. Planned in the 2023 filing.
On-site generation: diesel emergency generators, for use if grid power fails, per the project document and final report.
32 air-cooled chillers with closed water circuits, per the project document and the ministry's final report. The first plan used water cooling.
Potable water, estimated at 48.1 cubic metres a day at full build, mainly for staff, after an initial filling of the cooling circuits. The first plan was reported at up to 7.6 million litres a day.
Four neighbouring families filed an appeal with the Environment Ministry dated July 29, 2026, asking it to annul the permit. They say they were never notified or consulted though they live under 100 metres away, and report noise, night lighting, load bank tests and generator use. Footprint found no decision on it.
Water campaigners and a researcher won a 2023 ruling at the administrative court ordering the ministry to disclose how much water the earlier design needed. The ministry had cited industrial secrecy, and it appealed. Footprint didn't find the outcome.
Resolución Ministerial 644-2024 granted the permit, per the ministry's project page. In the scan Footprint opened, only the signature date, June 6, 2024, is machine-readable, so Footprint has not read the resolution's text. Montevideo Portal reports its conditions, including a two-year limit, a ban on using the Gonzalo "Gonchi" Rodríguez road during construction and an updated environmental management plan.
Google announced more than US$850 million for the site in August 2024 and tied it to growing demand for AI, which is why it is marked as an AI site.
Google's locations page describes the site in the future tense.
Last checked 2026-11-04.