Google data center (Cerrillos, Santiago)

Proposed · Documented · Location approximate

Not built. A court partly annulled the 2020 permit in February 2024, and Google said in September 2024 it would start again with air cooling. Chile's environmental service reportedly ruled on October 16, 2026 that the new design needs no environmental assessment. That ruling comes from news reports; Footprint could not open the file (PERTI-2026-7923).

Operator

Inversiones y Servicios Dataluna Ltda., a Google subsidiary according to OLCA

Location

Camino a Lonquén 9600, Cerrillos (as reported by El Pincoyazo)

About 23 hectares in Cerrillos and San Bernardo, Santiago, reported at Camino Lonquén and Avenida Lo Espejo. The point marks Camino a Lonquén on OpenStreetMap, not the site.

Power

  • Planned size, estimated: about 120 MW, Footprint estimate

El Desconcierto reports a 120 MW substation. OLCA reports 120.25 MW of generators: 44 diesel units, 43 of 2,750 kW and one of 2,000 kW, for emergencies and maintenance. These two reports describe different equipment with similar numbers and neither is a design figure Footprint read in the filing.

Power connection

Grid, original design: a power line joining the Pucará de Chena and Chena substations, per the court ruling. Not built. OLCA reports a 110 kV, 0.4 km line to Chena substation in the new plan.

Cooling

Original design: water cooling towers. Reported new design: 63 air-cooled chillers. The court ruling confirms a 2022 request to make this swap.

Water

Original design: groundwater from three wells in the Santiago Central aquifer, modelled at a maximum 169 litres per second. The new design wouldn't use water for cooling, but Google reportedly keeps the water rights.

Community

Chile's Second Environmental Court ruled for a local claimant on February 26, 2024. It found that the assessment did not consider climate change effects on the aquifer, partly annulled the permit and suspended the rest.

Local group Mosacat and the Observatorio Latinoamericano de Conflictos Ambientales (OLCA) asked the service to require a full assessment. They call the new filing a way around the ruling. Neighbours are studying legal action.

Reported diesel storage is about 696 tonnes. A 2025 rule change raised the threshold for an assessment from 80 to 1,000 tonnes, which is why this design doesn't need one, according to El Desconcierto.

Notes

Google told Chile's regulator in September 2024 that a new process would begin from scratch, for an air-cooled project at the same place, according to CNN Chile.

Footprint found no statement from Google on the 2026 filing. El Desconcierto says Google didn't respond.

The investment is about US$200 million for a Google campus.

In 2021 Diario Financiero placed the 23-hectare site at the crossing of Lo Espejo and Camino Lonquén, in Cerrillos and San Bernardo.