Project Camellia (OpenAI, Effingham County)

Proposed · Documented · Location approximate

Announced July 22, 2026. Effingham County's commissioners approved the site plan on Nov. 17, 2026, after tabling it on Nov. 3, WTOC reports. A commissioner said a development agreement is the next step. Footprint found no report of construction, so it is marked proposed. Lawsuits were pending in the latest reports read.

Operator

OpenAI, through its affiliate Octans GA LLC, which holds the land and filed the site plan

Location

Savannah Gateway Industrial Hub, a 2,600-acre industrial tract owned by the Effingham County Industrial Development Authority, near Rincon, Effingham County, Georgia. The campus would take about 1,440 acres of it. WTOC reports a wooded buffer along Hodgeville Road. No source read gives a street address. The point is FracTracker's location for this listing, rounded.

Power

Georgia Power says OpenAI is "expected to need approximately 3,200 megawatts (MW) of power" for the facility, under a 25-year agreement. OpenAI has agreed to up to 1,000 MW of flexible demand response, meaning Georgia Power can cut power delivered to the site at times of high demand. This is planned utility supply, not use.

Georgia Power said on Aug. 26, 2026 that the contract, with 3,200 MW of new demand, was approved as part of the Public Service Commission's process. CBS Atlanta reports PSC staff reviewed it and did not object, with no public vote, and that service is to be phased in from 2028 to 2032.

Georgia Power says OpenAI will pay the full infrastructure and electric service costs to serve the facility.

At the Nov. 17, 2026 meeting, the plan presented included four backup diesel generators for life-safety systems and no natural gas to power the computing systems, and the power agreement was unchanged, WTOC reports. These are plans; nothing is built.

Cooling

Closed-loop, per OpenAI as reported by the Effingham Herald. At the Nov. 3 meeting, the developer projected water use falling from 100,000 to 30,000 gallons a day with closed-loop cooling, WTOC reports. These are plans; nothing is built.

Community

Site plan: commissioners approved it on Nov. 17, 2026, two weeks after tabling it over questions about buffers and a berm, WTOC reports. Some in the crowd shouted "nay" and "shame" during the vote. An OpenAI project engineer said the revised design splits the original four buildings into six smaller ones. Reported commitments include a 20-foot berm along Hodgeville Road, a 300-foot vegetative buffer, a noise study with possible extra sound barriers, and a stormwater plan using ponds. Commissioner Roger Burdette said a development agreement comes next.

Pause on future applications: at the same Nov. 17 meeting, commissioners put off until January a decision on a proposed moratorium on certain future data center applications. Burdette said he wants to see how other places handle conditional zoning first, WTOC reports.

Zoning lawsuit: three residents sued on Sept. 2, 2026 in Effingham County Superior Court over Ordinance 2026-352, which commissioners approved on Aug. 4 to allow data centers on land already zoned industrial. They say required public hearings were skipped and ask for the ordinance to be voided, the Effingham Herald reports. The suit doesn't ask to halt the project.

Open meetings lawsuit: on Sept. 21, 2026 the conservation group One Hundred Miles and residents, represented by the Southern Environmental Law Center, sued the Industrial Development Authority in superior court. They allege it broke Georgia's open meetings and open records laws, listing the project only as "Project Gateway" on its July agenda and selling public land to Octans through a private agent. These are the plaintiffs' claims.

Racketeering lawsuit: on Nov. 6, 2026 the same three residents from the zoning case sued OpenAI OpCo LLC, Octans GA LLC, the authority, county commissioners and others in Effingham County State Court, WTOC reports. The 11 counts include fraud, civil conspiracy and violation of Georgia's RICO Act. They seek damages, not an order stopping the project. The allegations are unproven; the county doesn't comment on pending litigation.

Tax break: the authority approved a 50% property tax abatement for 15 years in July, the Effingham Herald reports. The authority says the land sale funds three years of $30 million payments to the county, partly to end county homestead property taxes in 2027 if voters approved a referendum.

SELC says the campus sits next to two elementary schools and less than 1,000 feet from homes. At the July open house, a resident raised water and power costs and the site's closeness to a high school and a park, WTOC reports.

Notes

OpenAI says the project is a $20 billion investment, and promises at least 400 permanent jobs and an $80 million community fund, per the Effingham Herald and WTOC.

Why this is marked as AI: OpenAI is the developer. Georgia Power's expected need of about 3,200 MW also puts it well over 100 MW.

The county hired Charles Abbott Associates to oversee the project and handle site issues such as truck traffic and construction noise, WTOC reported on Oct. 21, 2026.