Why Effingham County residents are suing OpenAI over Project Camellia

Last checked 2026-11-16. Compiled with AI help and checked against the linked documents.

On July 22, 2026, OpenAI and Georgia Power announced that OpenAI would build a data center campus in Effingham County, Georgia, about 45 minutes outside Savannah. The utility said the facility is expected to need about 3,200 megawatts of power. OpenAI called it a $20 billion investment.

Less than four months later, three residents who live near the site have sued OpenAI and their own county leaders under Georgia's racketeering law. This is how Project Camellia got here, and what is still undecided.

The site and the promises

The campus would sit in the Savannah Gateway Industrial Hub, a 2,600-acre tract owned by the Effingham County Industrial Development Authority, near Rincon. OpenAI's affiliate, Octans GA LLC, would use about 1,440 acres of it, according to WTOC.

OpenAI promised at least 400 permanent jobs, an $80 million community fund and a closed-loop cooling system that recirculates water, the Effingham Herald reported. "We have to earn the trust, we have to earn the right to build this," said Chris Lehane, OpenAI's chief policy officer.

County officials pitched it as a tax cut. "Current estimates project the average homeowner will see a 40% reduction in property taxes," County Manager Tim Callanan said, as quoted by WTOC. The authority approved a 50% property tax abatement for 15 years, the Herald reported. In August, the authority said money from the land sale would let it pay the county $30 million a year for three years, part of it to end county homestead property taxes in 2027 if voters approved a referendum in November.

Not everyone was won over. At the first open house, resident Arielle Rippley told WTOC, "Our water already is horrible," and raised power costs and the site's closeness to a high school and a park.

The power

The 3,200 MW figure is planned utility supply, not what the site uses. The campus hasn't been built. Under a 25-year agreement, OpenAI agreed to up to 1,000 MW of "flexible demand response," meaning Georgia Power can cut power delivered to the site when demand on the grid is high. Georgia Power says OpenAI will pay the full cost of the infrastructure needed to serve it.

The contract went through without a public vote. Public Service Commission staff reviewed it and declined to object, CBS Atlanta reported, and service is to be phased in from 2028 to 2032. Georgia Power said on Aug. 26 the contract was approved as part of the commission's process, and that its portfolio of large contracts would save customers money from 2029. That projection is the utility's, and covers many contracts, not this one alone.

Three lawsuits

The fights since then have been less about the data center itself than about how it was approved.

The zoning ordinance. On Aug. 4, county commissioners approved Ordinance 2026-352, which allowed data centers on land already zoned industrial. On Sept. 2, residents Michelle Finch-Mincey, Lehman Mincey Jr. and Raymond Carver sued in Effingham County Superior Court, saying the county skipped required public hearings, the Herald reported. They asked for the ordinance to be voided, not for the project to be stopped. "We're constantly being pushed out of being able to have a voice in this entire situation," Carver said. The defendants have filed a motion to dismiss, WTOC reports.

Open meetings. On Sept. 21, the conservation group One Hundred Miles and residents, represented by the Southern Environmental Law Center, sued the development authority. They allege its July agenda listed the project only as "Project Gateway," with no mention of a tax abatement they value at nearly $900 million, and that it sold public land to Octans through a private agent without the public meeting Georgia law requires. The group says the campus would sit next to two elementary schools and less than 1,000 feet from homes. "As Effingham residents, we have been kept in the dark," said Manjusha Sheobaran, who lives nearby.

Racketeering. On Nov. 6, the same three residents from the zoning case filed a nearly 50-page complaint in Effingham County State Court against OpenAI, Octans, the authority, the six county commissioners, the county manager and others, WTOC reported. Its 11 counts include fraud, civil conspiracy and violation of Georgia's RICO Act.

The complaint alleges the authority's CEO signed a nondisclosure agreement with OpenAI on Oct. 27, 2025, months before the announcement. It says the authority went into closed session for more than an hour on July 21 and approved an agreement with Octans, and that a deed conveying about 1,440 acres was signed on July 24 for a recited price of $10. It quotes an authority director saying that if the project had been made public, people would have opposed it over misinformation, and that "We're not a democracy."

These are allegations, and none has been proven. County leaders have denied the claims, and the board of commissioners doesn't comment on pending litigation. WTOC said OpenAI and the authority hadn't responded. The residents want damages and a jury trial, not an order halting the project. Their lawyer, Ben Michaud, told WTOC the case is about how the defendants procured the data center, not about AI itself.

A smaller plan, and a vote put off

On election night, Nov. 3, the commissioners took up the site plan. It had shrunk: six compute buildings of 471,000 square feet each, down from 30 at first, with 300-foot wooded buffers, WTOC reported. Projected water use had fallen from 100,000 to 30,000 gallons a day, the developer said, and building height had risen from 35 to 42 feet.

Commissioner Roger Burdette wanted a 20-foot earthen berm inside one buffer, and the developer wouldn't commit. "You came ill-prepared tonight," he said. Commissioner Beth Helmly raised the site's electricity demand: "I just feel like there's not enough time to make a decision." The board voted unanimously to table the plan.

What happens next

The site plan comes back on Nov. 17. The county has already hired an outside firm to oversee construction issues like truck traffic and noise. The three lawsuits are pending, and a ruling in any of them could change how, or how fast, the project moves. Footprint will update the record when the board votes.