PORTS-Pike Technology Campus

Proposed · Documented · Location approximate

Officials held a groundbreaking on March 20, 2026, but SB Energy's Sept. 21, 2026 SEC filing says the campus "is not yet under construction", while also saying it has "broken ground on the site for certain aspects of the project". On Oct. 20 the campus site said clearing and grading of the first phase would begin "over the coming weeks". Federal, state and siting board reviews are still open.

Operator

SB Energy (developer; says it will own and operate the data center site). Tenant: OpenAI. SoftBank controls SB Energy but is not named as operator or tenant here. The gas plants are a separate project: the siting case is Portsmouth Gas DevCo's, and SB Energy's filing says a SoftBank affiliate develops them

Location

Around the former Portsmouth Gaseous Diffusion Plant, south of Piketon, Pike County, Ohio. The campus spans leased federal land and private land. The point marks the coordinates in the May 2026 state water filing, rounded, for private land listed at 1003 Bobo Road, Beaver, OH. The site plan isn't final, so this marks one part of the campus.

Power

  • Design capacity: 10,000 MW

SB Energy's filing says utility service for the first 0.8 GW is covered by an Electric Service Agreement and Letter of Agreement with AEP Ohio, conditional on certain transmission upgrades. Agreements for 9.2 GW of transmission capacity are separate. It says these are "at various stages of execution" and need final regulatory approval.

The same filing says agreements to actually buy the electricity and capacity "have not been finalized or executed".

Who pays for the grid work: DOE's March 2026 fact sheet says SB Energy will pay for $4.2 billion in transmission with AEP Ohio. SB Energy's filing puts AEP's capital costs at about $5.1 billion, recovered with a regulated return through charges to SB Energy, which its leases pass on to OpenAI as operating costs. It warns the estimate may prove incorrect.

New lines: DOE's fact sheet lists 765 kV lines and four substations. AEP Ohio's roughly 50-mile 765 kV Baku-Gavin line through Pike, Jackson and Gallia counties needs siting board approval. AEP Ohio says the data center customer is paying for it.

First 800 MW: expected from 2028, largely using existing AEP infrastructure, according to Data Center Frontier.

SB Energy's filing says it has no agreement with any government body on the gas plants' funding, construction, ownership or operation. It understands the SoftBank affiliate has one. It says most of its data center backlog depends on those plants and the U.S.-Japan funding.

DOE's fact sheet says $33.3 billion in Japanese funding covers 9.2 GW of new gas generation, and that the project will reduce its power use or give backup power to the grid in emergencies.

Power connection

Planned, not built. Grid: SB Energy's SEC filing says the load is expected to be supplied by the PJM grid, through AEP Ohio, at a site where seven major high-voltage lines meet.

Planned, not built. Gas plants: SB Energy's filing describes "neighboring" gas generation of about 9.2 GW that it does not expect to own or operate. Portsmouth Gas DevCo's first phase, PORTS-Pike Energy Center I, is up to 2,000 MW of simple-cycle and combined-cycle gas, adjacent to DOE's site, with construction planned from early 2027 and operation in phases from the third quarter of 2028. It needs an Ohio Power Siting Board certificate (case 26-0746-EL-BGN, open).

Cooling

Closed loop, per the campus site. OpenAI describes it as closed-loop and air-cooled, as reported by Data Center Frontier and Ohio Tech News. These are company descriptions; the site is not built.

Water

An existing DOE water system, with new local water infrastructure the project helps fund, according to OpenAI as reported by Data Center Frontier. The campus site says demand "will be for the drinking water and restroom needs for employees". OpenAI says it will publish a site-specific estimate after final design. The gas plants' water use is not covered by these statements.

Community

Siting board case on the gas plant: 18 petitions to intervene from individuals and couples, all through the same lawyer, were filed Oct. 13 to Nov. 3, 2026, along with a petition from the Ohio Environmental Council and a notice of intervention by Pike County. The docket lists these; Footprint could not open the filings to read their arguments.

The City of Athens will prepare a petition to intervene, with written comments, in the siting board cases, the Athens County Independent reported on Nov. 12, 2026. It reports council has until Dec. 2 to submit written concerns, and that the mayor objects to simple gas turbines and wants air quality monitoring in place before the plants run. The paper names a second, larger gas plant case, 26-1070-EL-BGN, alongside 26-0746-EL-BGN.

The siting board's local public hearing is set for Dec. 10, 2026 at Piketon High School, and the evidentiary hearing for Jan. 6, 2027 in Columbus.

Streams and wetlands: Ohio EPA is reviewing a water quality certification for fill in 15 streams and 6 wetlands in the Lower Scioto watershed. Copies of two legal notices give different hearing details: Nov. 3 in Piketon, comments to Nov. 10, and, in the later one, Nov. 4 in Waverly, comments to Nov. 11. Footprint read the notices on a reposting site, not on Ohio EPA's.

Contamination: SB Energy's filing says the campus is "located on and around" a site "impacted with historic contamination" and under cleanup, and that it could face liability if cleanup fails and DOE's indemnity doesn't apply. DOE says SB Energy has committed to paying for faster cleanup.

Health concerns, from one side: former workers and residents told Farm and Dairy and The Post they link the plant to illness. A retired chemistry professor reported enriched uranium in samples from a school about four miles away. Ohio's health department told Farm and Dairy it has "not seen credible evidence" linking the plant to higher cancer risk. A former site electrician who leads a residents' group wants cleanup and people affected dealt with before construction.

The Post quotes a former engineer saying the project's Scioto River water could carry contamination if the site isn't cleaned up properly. That is his claim; no project document Footprint read says the campus draws from the Scioto.

Local reception is split in reports: Inside Climate News saw no organized campaign at a July 2026 open house and quoted a county commissioner in favor. WOUB describes "growing community opposition" in southeast Ohio. Local 12 reports most residents welcome it and quotes a local leader saying a dozen contaminated homes have been bought for the campus.

The campus site says nearby residents were told first-phase work may include blasting and temporary loud noise.

SB Energy and OpenAI say they have committed $80 million to a community fund.

Notes

Who is confirmed: SB Energy, whose SEC filing says a subsidiary has a phased lease with DOE, and that it will own and operate the data center site. OpenAI, which the same filing says leased the site in August 2026 for 20 years. NVIDIA, which gives a residual value guaranty on the first 4.25 GW of IT capacity, capped at $105 billion, with an option on the rest. Portsmouth Gas DevCo, the gas plant applicant.

Who isn't: no document Footprint read names SoftBank Group itself as operator or tenant of this data center. The filing calls SoftBank SB Energy's controlling shareholder and says a separate SoftBank affiliate develops the gas plants. No document read gives the Southern Ohio Diversification Initiative a role; Local 12 only quotes its director in support.

Names: the federal permitting council and Ohio EPA's notices say "PORTS Technology Campus", the state water filing says "Portsmouth Energy Project", and the developer's site says PORTS-Pike Technology Campus.

Land figures differ and the layout isn't final: the first phase at DOE's site is 189 acres, per DOE. The state filing says about 1,016 private acres. SB Energy's SEC filing says several thousand acres of private property. Data Center Frontier reports federal listings of about 1,300 and about 2,700 private acres.

Applicant names also differ: the state filing is from SE DC DevCo, LLC, with an SB Energy contact, while the legal notices name Portsmouth DevCo, LLC.

Federal review: the project gained FAST-41 federal permitting coverage in June 2026, with the Army Corps of Engineers as lead agency. Data Center Frontier reports Ohio EPA found the water filing incomplete in July. Echelon Reports says a Sept. 28 federal determination shrank the project area to avoid a cultural site and moved the target for the final federal decision to Jan. 29, 2027; Footprint could not open that determination.

Timing: SB Energy says the leases begin in stages from early 2028 to 2032. It warns the project may not be completed on schedule or at all.