All states

Data centers in Ohio

See Ohio on the map

67 sites · 3 researched · 43 local bans or limits in effect

Temporary data center bans are often called moratoriums.

Local bans and limits in effect

  • Butler County: Temporary data center ban · In effect · from 2026-06-16 to 2026-12-17 · source
  • Ashville: Temporary data center ban · In effect · from 2025-12-22 to 2027-01-04 · source
  • Barberton: Temporary data center ban · In effect · from 2025-11-10 · source
  • Blanchester: Temporary data center ban · In effect · from 2026-03-12 to 2028-03-12 · source
  • Cincinnati: Temporary data center ban · In effect · from 2026-04-01 to 2027-02-11 · source
  • Cleveland: Temporary data center ban · In effect · from 2026-10-19 to 2027-01-29 · source
  • Dayton: Data center ban · In effect · from 2026-06-24 · source
  • Findlay: Temporary data center ban · In effect · from 2026-04-21 to 2027-04-22 · source
  • Hubbard Township: Temporary data center ban · In effect · from 2026-02-10 to 2027-02-12 · source
  • Ironton: Temporary data center ban · In effect · from 2026-02-12 · source
  • Jackson Township: Temporary data center ban · In effect · from 2026-05-12 to 2027-05-29 · source
  • Jerome Township: Temporary data center ban · In effect · from 2025-09-03 to 2026-06-03 · End date has passed · source
  • Kent: Temporary data center ban · In effect · from 2026-04-15 to 2027-04-15 · source
  • Lake Township: Temporary data center ban · In effect · from 2026-03-03 to 2027-03-03 · source
  • Lordstown: Temporary data center ban · In effect · from 2026-01-05 to 2026-07-04 · End date has passed · source
  • Madison Township: Temporary data center ban · In effect · from 2026-06-01 to 2027-06-01 · source
  • Massillon: Temporary data center ban · In effect · from 2026-04-06 to 2026-08-14 · End date has passed · source
  • Maumee: Temporary data center ban · In effect · from 2026-02-02 to 2027-02-03 · source
  • Monclova: Temporary data center ban · In effect · from 2026-02-17 to 2027-02-18 · source
  • Monroe Township: Temporary data center ban · In effect · from 2026-03-09 to 2027-03-09 · source
  • Mount Orab: Temporary data center ban · In effect · from 2026-03-03 to 2026-09-03 · End date has passed · source
  • Muhlenberg: Temporary data center ban · In effect · from 2026-02-03 to 2027-02-03 · source
  • Norton: Temporary data center ban · In effect · from 2025-11-03 to 2026-05-02 · End date has passed · source
  • Plain Township: Temporary data center ban · In effect · from 2026-03-24 to 2027-03-27 · source
  • Pleasant Township: Temporary data center ban · In effect · from 2026-02-24 to 2026-08-24 · End date has passed · source
  • Ravenna Township: Temporary data center ban · In effect · from 2026-04-14 to 2027-04-22 · source
  • Richfield Village: Temporary data center ban · In effect · from 2026-03-03 to 2026-08-30 · End date has passed · source
  • Scioto Township: Temporary data center ban · In effect · from 2026-03-05 to 2027-03-06 · source
  • Shawnee Township: Temporary data center ban · In effect · from 2026-04-14 to 2027-10-14 · source
  • South Bloomfield: Data center ban · In effect · from 2026-02-01 · source
  • Sprigg Township: Temporary data center ban · In effect · from 2026-02-23 to 2027-02-24 · source
  • Springfield: Temporary data center ban · In effect · from 2026-07-14 to 2027-01-14 · source
  • St. Albans Township: Data center ban · In effect · from 2026-03-10 · source
  • Sunbury: Temporary data center ban · In effect · from 2026-04-15 to 2027-01-31 · source
  • Tiffin: Temporary data center ban · In effect · from 2026-04-20 to 2027-04-22 · source
  • Twinsburg: Temporary data center ban · In effect · from 2026-05-01 to 2027-05-01 · source
  • Urbana: Temporary data center ban · In effect · from 2026-03-03 to 2027-03-03 · source
  • Vienna Township: Temporary data center ban · In effect · from 2026-02-17 to 2026-10-16 · End date has passed · source
  • Washington Township: Temporary data center ban · In effect · from 2026-04-06 to 2027-04-06 · source
  • Waterville Township: Temporary data center ban · In effect · from 2025-12-17 to 2026-12-18 · source
  • Wellington: Temporary data center ban · In effect · from 2026-03-16 to 2027-03-01 · source
  • Williamsburg: Temporary data center ban · In effect · from 2026-03-12 to 2027-03-12 · source
  • Yellow Springs: Temporary data center ban · In effect · from 2026-05-18 to 2027-05-18 · source
Failed, retracted or expired (1)
  • Chillicothe: Temporary data center ban · Retracted · from 2026-08-24 to 2026-10-23 · source

Researched sites

Listed sites, largest first

Show all 64

Upcoming dates

  • Dec. 10, 2026: Public hearing on the PORTS-Pike gas plant

Articles

In the news

  • Ohio township moves to ban data centers where Amazon planned a campus: Butler County's Planning Commission recommended approval of a St. Clair Township zoning change that bars data centers as a primary land use, and the township's zoning commission approved it again on Nov. 10, 2026, the Journal-News reports. Trustees have the final say. About 358 acres of the 600 acres where Amazon Web Services planned an 18-building, $5 billion campus are in the township; Trenton and the landowners withdrew a petition to annex the land in September. Trenton voters approved a limit on data centers over 25 MW on Nov. 3. Amazon said it remains "committed to setting a high bar for responsible data center development in Ohio." source 1 · source 2
  • Meta Prometheus: Operating at New Albany, per Epoch AI, on a 740-acre tract in the New Albany International Business Park. About 1 GW cluster (reported size), described in September 2026 as still under construction while serving training jobs. source 1 · source 2
  • OpenAI Stargate Lordstown: Epoch AI lists it as under construction, with chips owned by SoftBank and used by OpenAI. Likely no more than 0.3 GW (Epoch AI estimate, inferred from OpenAI's combined figure). source 1 · source 2
  • PORTS-Pike Technology Campus: Expected to include a 10 GW data center and up to 10 GW of new generation, including 9.2 GW of natural gas (planned), per AP. SB Energy is leasing federal land at the former uranium plant, per The Register. SB Energy and AEP Ohio agreed a $4.2 billion transmission upgrade. source 1 · source 2
  • Google New Albany: Estimated 333 MW of IT power (Epoch AI estimate). SemiAnalysis puts the Google Columbus-area sites above 1 GW, with about 500 MW for AI, per Rich Miller. source 1 · source 2
  • Google Columbus: Estimated 303 MW of IT power (Epoch AI estimate); operating. source 1

Researched sites are Footprint's records. Listed sites and local rules: data provided by FracTracker Alliance (2026), accessed via fractracker.org/data-centers, shown as published and not reviewed by Footprint. These lists don't cover every data center.