Proposed · Documented · Location approximate
Aligned announced a groundbreaking on Sept. 10, 2026, and a gas line to the site is being built. Footprint found no first-hand account of how much work has been done. DEP's Oct. 31, 2026 notice still calls it a "proposed data center", and its air approval had not been issued as of that notice.
Aligned Data Centers, developer and operator. DEP applicant: Aligned.AI PA Owner. No tenant named. Frontier Group of Companies owns the industrial park and is separately converting the old power plant
Church Lane, Shippingport, PA 15077
Beside the former Bruce Mansfield coal plant, Shippingport Borough, Beaver County. The point is the coordinates in DEP's notice, rounded. DEP names Church Lane but gives no street number.
DEP's notice lists "~1.2 eKW" of solid oxide fuel cells. That unit looks like a misprint for a project this size, and Footprint has not read the draft approval to check it.
RBC analysts, as reported by Stocktwits, say Bloom Energy will supply fuel cells. Aligned's release does not name a supplier or mention fuel cells.
Data Center Frontier reports a National Fuel gas lateral of about 7.5 miles and about 205,000 Dth a day for a behind-the-meter data center, with service targeted for late 2026. Frontier's own page says 7.2+ miles.
Frontier's separate Shippingport Power Station is planned at 2,550 MW for the PJM grid, by its site page, with completion in late 2028 or early 2029. Its 2025 release described a larger plant. Shippingport's solicitor said in early 2026 this plant could eventually supply the data centers.
A draft DEP stormwater permit to Shippingport Power Station, LLC covers a 14.5-acre gas fuel yard on the old plant site, with "power island gas receiving equipment". PA Environment Digest ties it to the Aligned project; the notice does not name Aligned.
On-site generation, proposed: DEP intends to issue Plan Approval PA-04-00953A for solid oxide fuel cells, eight 4,680 hp and three 1,483 hp diesel emergency generators, a fire pump engine, four gas line heaters and 64 temporary generators. Application received April 13, 2026. Not issued as of the Oct. 31, 2026 notice.
Grid: Aligned says the campus "will use its own dedicated onsite power source rather than the local electrical grid", and expects to send excess power back to the grid once complete. No grid connection document was found.
Aligned says each building uses a closed-loop system recycling deionized water, and needs "zero water for operational cooling". This is a company statement. Data Center Frontier notes initial fill and normal building use still need water.
DEP will hold a public conference and hearing on the air approval on Dec. 3, 2026, 6 to 8 p.m., at the Shippingport Community Building. Written comments close 30 days after the Oct. 31 notice.
Shippingport Council granted several zoning modifications in early 2026, TribLive reports, and only four residents attended that hearing. A decision on going over noise limits during around-the-clock construction was still pending then.
The borough continued its conditional use hearing to March 31, 2026, and Data Center Frontier reports approval that day. Footprint has not read the decision. The application covers six tax parcels.
Aligned projects about 3,000 construction jobs and about 640 permanent jobs, and says $10 billion in regional investment. These are company figures. Its release also quotes Shippingport's mayor.
Roles: Frontier bought the old plant in 2022. Aligned bought about 650 acres from Frontier in July 2026 for about $223 million, according to trade reports. Neither company's own documents read here state the price.
DEP says total potential emissions will not exceed 59 tons a year of nitrogen oxides, 98 of carbon monoxide and 49 of VOCs. Emission limits on the approval keep the project out of major-source review programs.
TribLive described up to three buildings of more than 600,000 square feet each, a warehouse and a power generation pad. Holder Construction and Kokosing are named as Aligned's construction partners.
Frontier's July 2025 release said a partner would build a collocated data center "to support AI infrastructure", without naming it. Aligned's release does not mention AI.
Last checked 2026-11-05.