Proposed · Reported · Location approximate
Reported by Circle of Blue, inBuckeye, KTAR, KJZZ.
Approved by the city in August 2024. Local news said in March 2026 that no completion date had been released, and Footprint found no report of construction starting.
Tract, master developer. No end users named in sources read
South of Interstate 10 and west of Buckeye Municipal Airport, Buckeye, Maricopa County. 2,069 acres. The point is a rough mark in that area.
Local news says Tract is working with the local utility on infrastructure that "could support up to 1.8 gigawatts." No filing read, so it isn't in the power fields.
Planned on-site groundwater wells. Buckeye's water manager said Tract intends to drill wells and self-supply, later handing the system to the city. A city planning document, as described by Circle of Blue, restricts the site's groundwater use to 2,000 acre-feet a year, about 1.8 million gallons a day (Footprint arithmetic). That is a cap, not expected use. Tract declined to discuss its water plans.
The site's earlier plan was 9,706 homes, estimated to use 4,500 acre-feet of water a year. The mayor said in 2024 the project "reduces water demand."
Circle of Blue calls this a loophole: in 2023 the state stopped new housing developments outside Buckeye that rely on local groundwater, yet Tract plans to pump it.
A petition seeks to halt water-heavy data centers in Buckeye; local news put it under 100 signatures in March 2026. The mayor says he tells cities that reject data centers to send them to Buckeye.
Planned scale: up to 40 data centers and 20 million square feet.
Council unanimously approved a development agreement on Aug. 6, 2024, with up to $50 million in infrastructure reimbursement after the project produces $60 million for the city. Investment described as $20 billion over 15 years.
The city document behind the water cap (buckeyeaz.gov/home/showpublisheddocument/13925) refused Footprint's requests. Until someone reads it, this record stays Reported.
Last checked 2026-11-04.