Vantage DUB 13 (Profile Park)

Stalled · Documented · Location approximate

An Bord Pleanála refused permission on April 4, 2025. Vantage could apply again, and Footprint found no record of a new application, so this building is shown as stalled rather than cancelled. The refusal covers only this building, not the neighbouring DUB 11 and DUB 12.

Operator

Vantage Data Centers DUB11 Limited

Location

Townlands of Ballybane and Kilbride, Profile Park, Clondalkin, Dublin 22

South Dublin. The point marks Profile Park on OpenStreetMap, not the 3.79-hectare site.

Power

Vantage's energy statement, as summarised by the inspector, describes a 96 MW multifuel power unit for the wider campus, also described as generating 100 MW. It would temporarily power the campus while grid supply ramps up. The figures belong to the campus, not DUB 13.

Notes

Decision: refuse permission, dated April 4, 2025.

The board was not satisfied that DUB 13 itself had a fixed grid connection agreement, or that "permitted on-site gas powered generation would not be used as the primary energy source". It said that would go against the government's 2022 statement on data centres. It rejected its inspector's recommendation to grant permission.

The plan was one two-storey building of 12,893 square metres with 13 emergency generators. The inspector's report, written in 2024, describes the neighbouring DUB 11 and DUB 12 as under construction at that time.

This is part of a major campus.

Related

Sources

Last checked 2026-11-04.