What Loudoun County's data center pause does, and doesn't, stop

Last checked 2026-11-23. Compiled with AI help and checked against the linked documents.

On November 17, 2026, the county widely called the data center capital of the world voted to stop approving new ones for a while. Loudoun County's Board of Supervisors voted 7-1-1 to pause action on data center and substation applications, according to a release from Supervisor Juli Briskman's office, which led the effort.

The same release says Loudoun has about 245 data center buildings built or under construction, around 58 million square feet, with another 55 million square feet approved or in review. The pause doesn't affect what is already built. Here is what it does cover, what it leaves out, and why the county didn't call it a moratorium.

What the vote does

The resolution pauses the board's consideration of "legislative" applications, the kind that need a board vote, while the county finishes the second phase of its data center rules. Bisnow reports that this means rezonings and special exceptions. The pause is retroactive to September 15, when the board first voted to pursue it.

Applications don't stop moving entirely. Developers can still submit them, and county staff and the Planning Commission keep reviewing them, the county says. What waits is the final step: board public hearings and votes. "The pause would not cause any applications to become inactive," the county's notice says.

County staff count 33 active legislative applications for data centers and substations, and the release from Briskman's office says "the vast majority" could be affected. The second phase of the rules is expected to be finished in July 2027. When it is, developers whose proposals were paused will be expected to update them to meet the new rules, the release says.

Why it isn't called a moratorium

The county attorney advised that a full moratorium on data center approvals would not be legal, the county says. Instead the board is using time it already has. Under Virginia law, it has up to 12 months from an application's Planning Commission hearing to take final action, unless the applicant agrees to more time.

That limit cuts both ways. At least nine applications are expected to reach their 12-month deadline before the new rules are done, according to the release. Staff will ask those applicants to agree to wait. If they don't, their applications can go to the board before the rules are finished.

County Attorney Leo Rogers told the board the pause is legal, but that he sees a "real threat of litigation" from applicants, Bisnow reports. When the board took its first vote in September, Chair Phyllis Randall said the measure was "not a moratorium," but a way to give the county time to write new laws, WJLA reported.

What it leaves out

Several kinds of projects keep going:

  • By-right and grandfathered projects. The county attorney's office found the board has no authority to pause administrative applications, including those grandfathered under a 2025 resolution, the release says. Bisnow counts 15 such projects totaling 10.5 million square feet that can continue, and says site plans and subdivision plans still proceed.
  • The Route 28 Tax District. The action doesn't apply to legislative applications there, the county says.
  • Grid reliability substations. Substations found to qualify are exempt from the pause, though they still need a board vote, according to the release. The county says the board may also consider exceptions when a decision deadline is about to run out.

Who voted how

Supervisor Kristen Umstattd of the Leesburg District voted no, and Supervisor Caleb Kershner of the Catoctin District abstained, Bisnow reports. The same split came in September.

"Loudoun County residents have been begging us to get our arms around unchecked data center sprawl," Briskman said in the release, adding that her office got more than 200 emails backing the pause in a week. "I believe it is irresponsible for Loudoun County to continue approving data centers while we are actively working to strengthen the regulations that govern them."

Not every resident agreed. At the September meeting, one told the board, "We should not impose a pause on building data centers," and asked the county instead to hold owners to a higher bar, NBC Washington reported. Another described a family near a data center whose young children have breathing illnesses, which the speaker linked to a gas turbine generator that runs constantly. NBC didn't name the site.

What the new rules could change

Loudoun already ended most by-right data center building in March 2025, so new proposals need a special exception approved by the board. The second phase looks at where data centers and substations can go, including how close they can be to homes, schools and other sensitive places, the release says. It will also cover building heights, noise and on-site power generation.

On-site power is already an issue in the county. Vantage VA2 in Sterling runs on eight gas turbines under a state air permit, and neighbors have complained about the noise for months. On November 5, two weeks before the pause, the board approved Dominion's Golden substation after Dominion agreed to supply Vantage around 2028, Loudoun Now reported. The turbines would then be dismantled, according to that report.

What it means for the map

The pause is about approvals still being sought. It doesn't order any running site to stop or change, and Footprint hasn't found a list of the 33 paused applications. The Loudoun records on the map, such as Equinix's Ashburn campus and Microsoft's Leesburg site, are already built. Amazon's former GW Ashburn campus, where Amazon dropped a data center plan in October, is waiting on a separate rezoning that would bar data centers.