Homer City Energy Campus

Proposed · Documented · Location approximate

The gas plant is under construction, with more than 2,000 workers. The data centers are not approved. Indiana County accepted AWS's plan for review on Oct. 14, 2026 and has until Jan. 12, 2027 to decide. AWS expects to start in December 2026 if it gets its permits.

Operator

Amazon Web Services (applicant Amazon Data Services, Inc.) proposes the data centers. Homer City Redevelopment and Homer City Generation LP are building the gas plant and redeveloping the wider campus

Location

1750 Power Plant Rd, Homer City, PA 15748

Former Homer City coal plant, Center Township, Indiana County. The point is the federal EIA location for the generating station, not the data centers. AWS's six building sites (Bruner, Helen, Green, West, Harvey/Gaston, Rura) are in Center and Blacklick townships.

Power

DEP's air permit covers seven GE Vernova 7HA.02 combined-cycle turbines, ten Mitsubishi FT8 simple-cycle turbines, ten 2.5 MW and two 1.0 MW diesel emergency generators, and seven cooling towers.

Plant size differs by document: DEP's review memo says 4,678 MWe, the developer says up to 4.4 GW, and AWS's narrative says 4.5 GW. These are generation figures for the gas plant. No document read gives the data centers' electricity use.

AWS says it will pay all costs for any new electrical infrastructure needed to serve the campus.

The developer projected first power in 2027. That is a company projection.

Power connection

AWS's narrative says power "will be acquired from FirstEnergy, supported by" the gas plant being built on the campus. This is a stated plan, in an application not yet decided.

On-site gas plant: DEP Plan Approval 32-00457A, issued Nov. 18, 2025 to Homer City Generation LP, expires May 31, 2027. It is under appeal. DEP says the approval covers the power plant only and "does not authorize the construction or operation of any data centers".

Cooling

AWS's narrative describes "non-contact cooling water" returned to the Homer City station for reuse. It gives no volume or cooling design.

Water

AWS says existing water-withdrawal rights and water treatment facilities planned by the developer. It projects the combined campus will keep to the "historic water withdrawal rate" and gives no figure.

Community

More than 100 people attended the county planning commission's Sept. 9, 2026 meeting, WJAC reports, and dozens spoke. Concerns included noise, water, pollution and farmland. The commission tabled the plan, then accepted it for review on Oct. 14. It is on the Nov. 18 agenda. Staff say acceptance is not approval.

Two appeals of the air permit are at the state Environmental Hearing Board: one by Clean Air Council, PennFuture and Sierra Club (2025-135-L), one by young people aged two months to 21 (2025-136-L). The board refused to merge them on March 23, 2026. Footprint found no ruling on the merits.

The groups' appeal says DEP failed to follow its environmental justice policy, naming Center Township as an environmental justice community. This is their claim as a party. The youth appellants argue their constitutional rights are violated, and their lawyers say the case is in discovery.

Capital & Main reports the plant has had an uncapped allotment from Two Lick Reservoir since 1968, and that the reservoir is shared with a local water utility. The utility's manager said of data centers' water needs: "That's something we probably cannot provide."

A developer spokesperson said cooling and water decisions would be left to its data center clients, according to the same report. A neighbors' group, Concerned Residents of Western Pennsylvania, opposes the project.

AWS says it does not expect to seek incentives that cut property tax assessments, and will work with the developer on a community benefits agreement. It projects 1,500 to 2,000 permanent jobs at full build.

Notes

Plan size differs. AWS's Aug. 27, 2026 narrative says 39 data centers and about 2,200 acres to be acquired. Local reports in September and October say 36 and, in the later ones, about 1,100 acres. Footprint did not read the full county application and could not reconcile them.

Each building would be two stories and about 70 feet tall, at about 225,000 square feet. AWS plans six phases from December 2026 to mid-2036.

The air permit caps the plant at 17,551,454 tons of greenhouse gases a year, as CO2 equivalent, and 1,142.8 tons of nitrogen oxides.

A draft state water permit would send up to about 6.84 million gallons a day of gas plant cooling tower wastewater to Blacklick Creek. Raw water for that cooling comes from Two Lick Creek. This is the power plant, not the data centers.

The developer reported more than 1,800 workers on site in September 2026, and a later report says more than 2,000 by Oct. 20. The work described is led by the gas plant's contractor, Kiewit; the data center plan was still under county review.

EIA's generator list shows the station as a planned 4,396 MW gas plant, expected July 2028.

The developer's project page describes the campus as serving "AI-driven hyperscale data centers". AWS's narrative says the campus "will support cloud computing services".

Related

More in Pennsylvania

Sources

Last checked 2026-11-05.