Homer City: a retired coal plant, a huge gas plant, data centers not approved

Last checked 2026-11-05. Compiled with AI help and checked against the linked documents.

On September 17, 2025, residents lined up at a microphone at Indiana University of Pennsylvania to ask about a gas plant planned for their area. John Dudash, 89, didn't speak. The next morning, Capital & Main reported, he emailed two state environmental staffers.

"First of all, the project will not be stopped," he began, then offered advice on air monitoring.

The old plant

Homer City once had the largest coal plant in Pennsylvania, at about 2 gigawatts, Capital & Main reported. It closed in 2023 after years of financial trouble and two bankruptcies. In March 2025, the same private equity owners, operating as Homer City Redevelopment, brought down its smokestacks. Weeks later they announced it would reopen with data center customers.

At the hearing, many wore neon shirts with union logos. Shawn Steffee, a business agent with the Boilermakers union, took the microphone. "Everybody speaking about jobs, there will be jobs, and there will be local jobs," he said, to the loudest applause of the night.

Others doubted the scale. Robin Gorman, the developer's spokesperson, said the owners foresee 10,000 construction jobs and 1,000 "direct and indirect" permanent ones. Sean O'Leary of the Ohio River Valley Institute said data centers average as few as 10 employees and as many as 110, by his calculations.

A permit for the plant only

The state approved the air permit on November 18, 2025, after more than 550 comments. It was "a major milestone," said Corey Hessen, CEO of Homer City Generation. The company said the plant should serve data centers and potentially thousands of homes.

The regulator drew a line. The approval "does not authorize the construction or operation of any data centers," it wrote, and "no specific use of adjacent areas have been confirmed."

The permit caps the plant at about 17.5 million tons of greenhouse gases a year. Three environmental groups and 15 young people, aged two months to 21, appealed separately. The state hearing board refused to merge the cases in March 2026. Footprint hasn't found a ruling on the merits.

Construction went ahead. Kiewit arrived in October 2025, and the developer reported more than 2,000 workers on site by October 2026.

How big, and for whom

The plant's size depends on the document: 4,678 MWe in the state's review memo, up to 4.4 gigawatts from the developer, 4.5 gigawatts from AWS. All are on-site generation. Footprint hasn't found a document giving the data centers' electricity use. The developer projected first power in 2027, while the federal generator list expects July 2028.

On August 28, 2026, Indiana County received a plan from Amazon Data Services. AWS's narrative describes 39 data centers on about 2,200 acres, two stories each, built in phases through 2036. Later local reports say 36 buildings and 1,100 acres. Footprint couldn't reconcile them.

AWS projects 1,500 to 2,000 permanent jobs. It says it doesn't expect to seek incentives that cut property tax assessments, and will pay for any new electrical infrastructure. Power would come from FirstEnergy, "supported by" the gas plant.

Water

Since 1968, Capital & Main reported, the plant has had an uncapped allotment from Two Lick Reservoir, which it shares with a water utility. A drought plan says the plant drew so much in 1985 that, "had a significant rainfall not occurred," the reservoir "may have faced total depletion."

Rob Nymick, manager of the Central Indiana County Water Authority, said towns could share water with the gas plant. Data centers were different. "That's something we probably cannot provide." Gorman said water and cooling decisions would be left to clients.

AWS says the combined campus will "maintain the historic water withdrawal rate." It gives no figure.

The courthouse

On September 9, 2026, more than 100 people came to the county planning commission's meeting at the courthouse, WJAC reported.

"Thank you for this opportunity to directly tell Amazon that Indiana County does not welcome you," one resident said. Another said dashed lines on an AWS map crossed the speaker's property, and that no one had made contact. A third, hopeful about work for her son, thanked the company "for bringing hope." The commission tabled the plan while questions were addressed. AWS said it would keep answering them.

What's unresolved

On October 14, the commission accepted the plan for review, with a deadline of January 12, 2027, and put it on the November 18 agenda. Byron Stauffer of the planning office said that isn't a formal acceptance of the plan. AWS anticipates starting construction in December, subject to permits.

So the plant is rising while the data centers it was announced to serve wait for a decision, and Footprint hasn't found a ruling on the merits of either appeal. How much water and power those buildings would use hasn't been stated in anything Footprint has read.