Data centers in Mississippi

See Mississippi on the map

13 sites · 4 researched · 1 local ban or limit in effect

Temporary data center bans are often called moratoriums.

Local bans and limits in effect

  • Jackson: Temporary data center ban · In effect · from 2026-07-14 to 2027-01-14 · source

Researched sites

Listed sites, largest first

Upcoming dates

  • End of Nov. 2026: Gun Range due to start, Elon Musk says
  • Dec. 2026: Spam due to start, Elon Musk says
  • No date public: Possible $6.1 million in stormwater penalties

Articles

In the news

  • Coolant spill at xAI's Stanton Road power site: Between 5,000 and 6,000 gallons of DOWFROST HD, a propylene glycol heat transfer fluid, escaped from a tank at xAI's Stanton Road site and flowed into a nearby drainage ditch, the Mississippi Department of Environmental Quality told FOX13 on Nov. 15, 2026. xAI said a contractor set up a hose on a mobile tank wrongly, the release was stopped quickly and cleanup began within hours. MDEQ said there was no immediate threat to public health or safety and recovery would continue for several more days, with xAI responsible. Keshaun Pearson of Memphis Community Against Pollution called it a "wake-up call." The Stanton Road turbines power MACROHARDRR and Colossus 2. source 1
  • xAI Southaven turbines and MACROHARDRR: Mississippi regulators granted an air permit for xAI's Southaven facility in March 2026. The proposed permit was for over 40 permanent gas turbines, held by xAI affiliate MZX Tech (on-site generation). The permit drew unanimous opposition at the Southaven public hearing. Colossus 2 was already powered by roughly 20 turbines before the permit, per E&E News, which says xAI was accused of breaking federal clean air rules. On Nov. 10, 2026, after a two-day evidentiary hearing, the state Permit Board voted to stand by the March permit, with Agriculture Commissioner Andy Gipson the only no vote, per DeSoto County News. Opponents could still go to court. source 1 · source 2 · source 3 · source 4
  • Amazon Madison Mega Site: Estimated 284 MW of IT power; Anthropic is only a possible user (Epoch AI). Amazon announced a planned $11 billion expansion in Madison County, with 700 jobs. Broke ground on the first $10 billion project in May 2024. source 1 · source 2 · source 3

Researched sites are Footprint's records. Listed sites and local rules: data provided by FracTracker Alliance (2026), accessed via fractracker.org/data-centers, shown as published and not reviewed by Footprint. These lists don't cover every data center.