Last checked 2026-11-05. Compiled with AI help and checked against the linked documents.
On September 19, 2025, people entering the Doña Ana County Government Center in Las Cruces passed metal detectors and extra armed security. Commissioners were to vote on a $165 billion industrial revenue bond for Project Jupiter, a data center campus planned for Santa Teresa.
Three times, Commissioner Susana Chaparro moved to postpone, saying no one had had time with hundreds of pages of documents. Some had arrived the night before, with missing pages. No one seconded her. The county's bond attorney said the missing pages were closing documents and legal background that would come later.
Seven hours in, the bond passed 4-1, and shouting broke out. "This is capitalism run amok," Balm Leavell, 89, told a reporter.
The Albuquerque Journal explained that the bond commits no county money and creates no public debt. The county holds title and leases the property back. The $165 billion is the most the developers, BorderPlex Digital Assets and STACK Infrastructure, expect to invest over 30 years.
They agreed to pay $360 million over 30 years instead of taxes, plus $50 million for water and wastewater upgrades. Critics called that a pittance. Commissioner Manuel Sanchez said the project was a chance "to build that base so we can offer more to our residents." BorderPlex chairman Lanham Napier cited "a national focus to secure these critical digital assets."
No tenant had been publicly named. Oracle and OpenAI were later identified as the users.
Derrick Pacheco, a Las Cruces resident, sued that October over the bonds, alleging they came before the county's planning commission had voted on zoning. He used ChatGPT to help him write the suit. In June 2026, Judge James Foy dismissed it for the second time, with leave to refile. "I think I told you this last time: Go get a lawyer," Foy said. Lawyers for Oracle, the county and developer Yucca Growth Infrastructure called another try a "third bite at the apple."
"It's the supercomputer fighting the supercomputer," Pacheco said.
The New Mexico Environmental Law Center alleges that commissioners approved incomplete applications, some marked "draft." In March, a judge ordered the county to produce the full record, rejecting its bid to dismiss. The county had called the suit "an improper attempt to use the courts to halt legislation they dislike."
The center's second suit alleges an open-meetings violation. The New Mexico Foundation for Open Government sued in June, alleging the county withheld emails under an exemption meant for terrorism response plans. That made at least four pending suits. The commission chair and county manager didn't respond to Source New Mexico.
The plan is for a private power system on site. It was first designed around 2.2 GW of gas turbines, according to reports. Reports say the State Land Office rejected rights-of-way for a gas pipeline, and that Oracle later switched to Bloom Energy fuel cells, which also run on natural gas.
That is planned on-site generation of up to 2.45 GW, and it needs an air permit. Separately, Epoch AI estimates 1,750 MW of IT power by late 2028. In June 2026 satellite images, Epoch saw no operating buildings.
The state Supreme Court paused the proceeding in August, then lifted the stay on September 17 without giving reasons. "We believe the rules of this proceeding were stacked against meaningful public participation," said Mariel Nanasi of New Energy Economy, which brought the petition. Its petition linked a hearing officer's schedule reversals to a July meeting between the governor and Oracle. The governor has denied any interference.
On September 24, reports said Oracle had sent a force-majeure notice tied to the 1,400-acre campus. Capacity, citing Bloomberg, wrote that if both sides accept a power-related force majeure, Oracle could delay rent by three years. It would still owe other costs, and Oracle isn't seeking to leave, Capacity said.
"Project Jupiter remains on our planned schedule," Oracle said. Spokesman Michael Egbert called such notices "commonplace in developments of this scale." Blue Owl, which owns STACK, said the notice "does not change the financial commitments."
In October, Oracle announced a change that it said cuts permitted emissions by about 35%. The Journal reported that the cut comes from a 1,600 MW operating limit in the permit language, not engineering that reduces emissions. "These are not minor corrections," Nanasi said, seeking dismissal. Hearing Officer James Browning denied that and kept a December 7 public hearing.
Capacity earlier reported a November 23 deadline for the permit decision. Footprint hasn't found how that date fits with the December hearing.
The pipeline still needed federal authorization at that point. An Oracle executive told commissioners in July that the project would turn to the grid if the permit is unavailable. Footprint hasn't found rulings ending the remaining suits, or an amended complaint from Pacheco.