Meta's Hyperion, a vacated subpoena and a 4,500 MW figure in Louisiana

Last checked 2026-11-05. Compiled with AI help and checked against the linked documents.

"I'm not for change. I don't change my furniture around or nothing," Joyce Piercy, 81, told WAFB in May 2026. Two of her great-grandsons were working at sites tied to Meta's data center in rural Richland Parish, Louisiana. "It's helping the community," she said, "but it's making it rough for us old folks, trying to drive in all that traffic."

A campus that kept growing

Meta announced Hyperion in December 2024 as a $10 billion project. By August 2026, Biz New Orleans reported, it expected more than $50 billion and 5 gigawatts of "computing capacity."

Regulators approved three gas units for the first phase in August 2025, 4-1. In March 2026, Entergy Louisiana asked to add 5,278 MW of generation, plus batteries and transmission, for an adjacent site held by a Meta subsidiary.

In a parish of about 20,000, tax assessor Lee Brown told WAFB that at least 4,000 extra people now live and work there, and that a $600-$700 rental had reached $2,500. He expects $30 million in property tax from Meta over three years. Meta said the site wasn't designated residential and that it is "committed to being a good neighbor."

The subpoena

On July 10, Chief Administrative Law Judge Melanie Verzwyvelt granted two of five requests from the Alliance for Affordable Energy and the Union of Concerned Scientists. Meta would have to produce evidence on its investment and permanent jobs, and on the amount of electricity the site would need.

Entergy and commission staff opposed the subpoena. Entergy said it had given specific support for its claims. Meta, not a party to the case, argued that disclosure of trade secrets "will cause irreparable injury." On August 4, the judge found that Entergy lacked the data underlying Meta's power projections, and that existing rules could protect anything confidential.

August 12

The fight reached the five commissioners on August 12, 2026. The transcript records most of what follows.

Chairman Eric Skrmetta moved to defer, saying related issues could be decided together in September. Commissioner Davante Lewis objected, saying "speed cannot only be used when it values Entergy and Meta." Vice Chairman Jean-Paul Coussan then moved to reverse the judge.

"It's difficult for anyone to argue against the generating stations without knowing what Meta's load actually is and how they developed it," said Susan Stevens Miller, the groups' Earthjustice attorney.

On jobs, Coussan replied that the information "is readily accessible to the public by watching -- by watching the news and understanding what's happening," while acknowledging the groups wanted "more granular data." Skrmetta reminded the room that judges make recommendations: "The Commissioners make the decisions."

Lewis wanted to question Meta's lawyer. Skrmetta said he could come up or not: "It's his choice."

"I refuse to come up," said Weston Adams, Meta's outside counsel.

Lewis voted no. Coussan, Skrmetta and Mike Francis voted yes, and Foster Campbell was absent. The order vacating the subpoena followed on September 17, 3-1.

The groups appealed to a state court that month, saying commissioners gave no reason. Footprint hasn't found a ruling.

October 7

Eight weeks after the vote, Entergy Louisiana CEO Phillip May took the stand before Verzwyvelt. The Advocate reported that he disclosed, for the first time, the amount of power Meta will use: 4,500 MW. The paper said Entergy had closely guarded it. Footprint hasn't read the hearing transcript.

May called the project a "transformational investment" with protections for ratepayers, and said the contract makes Meta pay for its power even if it leaves early.

Miller noted that some critics say "data centers are being overbuilt" and could become a liability. "I don't know that we have exactly looked into that," May said, countering that Meta has revenue unrelated to AI.

Opponents warn customers could carry costs if Meta leaves after its 20-year contract, since three plants would be depreciated over 32 years. Entergy says its system would still need them.

The numbers are different things

  • 4,500 MW: the amount of power Meta will use, as The Advocate reported the testimony. The report doesn't say whether that covers the whole campus. Not current use.
  • 5 GW: "computing capacity," Meta's figure. Not a documented electrical load.
  • 5,278 MW: proposed generation, not approved.
  • 2,262 MW: approved generation, according to an intervenors' filing.
  • 0 MW now, 1,632 MW projected for early 2028: Epoch AI's estimate of power for the computers.

Footprint hasn't found a document giving requested grid capacity.

What's unresolved

The commission is scheduled to consider the expansion's power plan on December 16, 2026, and four of its five members have previously backed Entergy's plans. The court appeal is pending. Footprint hasn't found the analysis behind the 4,500 MW made public.